Indian Railway Codes and Manuals-Engineering code-Chapter- 13 (XIII)
CHAPTER
XIII
INITIAL
RECORDS
1301. Initial Records on the Engineering Department relate to the
payment of the following :
- (i)
Wages of labourers and members of work charged establishment.
- (ii)
Payments to contractors and others for work done, services rendered and
materials supplied.
- (iii)
Pay and allowances of Construction staff and other miscellaneous payments.
The method of preparation of initial records in
all these cases is described in the following paragraphs.
1302. Muster Sheets.--The wages of labourers and work charged
establishment are charged through the muster sheets on which their daily
attendance and absences are marked. Since some of the labour employed may be
those governed by the Minimum Wages Act, 1948, the Muster Roll form prescribed
under this Act has to be followed if separate Muster Rolls are adopted. The
prescribed form is available as Form No. 91 in Appendix 9 of Indian Railways
Establishment Manual.
1303. Register of Wages.--Where separate Muster Rolls are used, since some
of the labour employed may be governed by the Minimum Wage Act 1948, a Register
of Wages as prescribed [Form E 1303] under this Act has to adopted. Alternately
the combined Muster Roll and Labour Pay sheet indicated in para 1304 may be
adopted as pay sheet or register of wages.
Form E.1303 (Continued to........ List of
forms)
1304. Muster Roll and Labour Pay Sheet.-- A combined Muster Roll and Labour Pay
Sheet can also be adopted. For this purpose the following form may be
used.
Form E.1304 (Continued to........
List of forms)
1305. One muster sheet should
be maintained for each gang of labourers or a convenient group of work-charged
establishment. Before the commencement of a wage month, the Assistant Engineer
should issue the requisite number of blank muster sheet forms to each
supervisor for the purpose of recording the daily attendance of the labour
working under him. Each muster sheet form so issued should bear the initial of
an officer not below the rank of Assistant Engineer on the top right corner as a
token of its authenticity. The muster sheet should be written up daily by the
person deputed for the purpose, generally the subordinate under whom the labour
or the work charged staff concerned is employed.
1306. The daily attendances and absences of labourers should be recorded
in the muster sheets in such a way as---
- (i)
To facilitate the correct calculation of the net wages of each person for
the period of payment.
- (ii)
To render it difficult to tamper with or make unauthorised additions to or
alterations in, entries once made; and
- (iii)
To facilitate the correct classification of the cost of labour by works
and sub-heads of works where necessary.
The subordinate maintaining a muster sheet
should, therefore, note in words the total number of persons present on each
day and give brief remarks as to the work or work on which the labour was
employed each day at the bottom of the sheet.
Assistant Engineers should check muster sheets
as frequently as possible and record on the spot the number of men present in
words and in ink, over their initials.
1307. At the end of every wage month the muster sheets should be
closed, the amount of gross wages due to each labourer or work-charged employee
should be worked out and the totals struck. The muster sheets so completed
should be collected by the supervisor and submitted through the Assistant
Engineer to the Executive Engineer with an abstract of all muster sheets submitted
for checks and payment. In the office of the Executive Engineer the muster
sheets should be checked under the supervision of the Divisional Accountant
before they are sent to the Accounts Officer for arranging payment.
1308. Payments of muster sheets should be made and witnessed by
the officer of the highest standing available on the spot. The witnessing
officer should certify to the payments individually or by group, a the same
time, specifying both in words and in figures, at the foot of the muster sheet,
the total amount paid on each date. Assistant Engineers should witness payments
of all labour under one or more subordinates each month. This should be done
without warning.
1309. Unpaid amounts, should, in the case of a muster sheet for men
employed on several works, be considered as relating to the most costly work in
the group and subsequent payments of unpaid amounts should be debited to that
work, if the accounts of the work are still open, otherwise to the same head of
the capital account.
1310. Unpaid Wages.-Unpaid amounts on muster sheets will be paid on
Extract Muster Sheets/Pay Orders. In all such cases a counter reference should
be made by the executive officer against the corresponding entry in the Unpaid
Wages list form A.1954 supplied by the Cashier. This precaution is necessary to
avoid more than one payment. Unpaid amounts on muster sheets will not be posted
in the Register of Works or Accounts.
1311. Muster sheets should never be prepared in duplicate. They should
not ordinarily pass beyond the office of the responsible disburser. The
Accounts Officer may, however, send for the paid muster sheets in connection
with any accounts discrepancy or any investigation.
1312. The payment of daily labour through a contractor instead of
through muster sheets and labour pay sheets in the usual way is objectionable
in principle. In a case of great emergency it may sometimes be found impossible
to employ labour otherwise than through a contractor. Should it be possible in
such cases to determine the quantities of work done after its completion or at
intervals during its progress the payment to the contractor should be on the
basis of work actually excecuted. But if, as in the case of urgent repair of
breaches of lines this method of payment is not practicable, it is permissible
to pay the contractor on the basis of number of labourers employed day by day,
his own profit or commission being included in the rates allowed. When this
course is adopted, a report of the number of labourers of each class employed,
day by day should be made in the following form (Form E. 1312) by the
subordinate incharge of the work daily to the Assistant Engineer to enable the
latter to keep a check on the expenditure and to deal with the contractor's
claim when received. To avoid disputes the contractor should be asked to sign
the Daily Report of Labour (sent by the subordinates) in token of their
acceptance. The use of muster sheets or the measurement book is not permissible
in such cases.
Payment to Suppliers and Contractors
1313. Record of
Measurements.-Payments for all work done
otherwise than by departmental labour and for all supplies are made on the
basis of measurements recorded in Measurement Books (Form E. 1313 given below)
in accordance with the rules contained in this Chapter.
1314. The
measurement books should be considered as very important record. All the books
belonging to a division should be numbered serially and a register of them
(Form E. 1314 given below) should be maintained in the divisional office
showing (1) the serial number of each book, (2) the name and designation of the
person to whom issued, (3) the date of issue and (4) the date of its return, so
that its eventual return to the divisional office may be watched. A similar
register (Form E. 1314 given below) should also be maintained in the
sub-divisional office. Books no longer in use should be withdrawn promptly even
though not completely written up. The eventual return of all measurement books
should be insisted on. They should be carefully preserved for ten years. To
ensure this, measurement books should be carefully listed and made over to the
open line authorities when the construction divisions are closed.
1315. Recording of Measurements-On the open line
organisation of the Railways the following powers can be exercised in recording
measurements :--
(i) Inspectors of Works and Permanent Way Inspectors in Gr. II
(Rs. 1600-2660) and Gr. I (Rs. 2000-3200) can record all measurement including
ballast measurements subject to the test checks given below, but cannot record
earth work sectional measurements unless they are specifically nominated by the
Assistant Engineer on considerations of competency and reliability. A 10% check
by the Assistant Engineer is necessary for works costing upto Rs. 25,000/-, if
the value of the work exceeds the estimated cost by more than 10% and for works
costing above Rs. 25,000/- a 20% check by Assistant Engineer is necessary. In
the case of ballast and pitching stones measurements a 100% check on quality
and the quantity by the Assistant Engineer is necessary. The Check of the
Assistant Engineer in respect of earth work sectional measurements may be done
at his discretion. Those Inspectors in Gr. I (Rs. 2000-3200) may finalize
measurement for work upto Rs. 10,000/- even when the total value of the works
exceeds the estimated value by more than 10%.
(ii) Inspector of Works and Permanent Way Inspectors in Grade III
(Rs. 1400-2300) when they hold independent charge, can record measurement for
works costing upto Rs. 25,000/- each, subject to a test check of 20% by the
Assistant Engineer.
(iii) Sub-Overseers, Mistries having a diploma in Engineering and
having more than three years of service and those not having a diploma in
Engineering but having six years experience to be nominated by name by the
Divisional Engineer can record measurements of works upto Rs. 10,000/-, subject
to a test check of 20% by the Inspector of Works.
(iv) Recording of Measurement of Elec. open line &
construction Works.
(a) Shop Supdt./ Chief Traction Foreman, in
grade Rs. 2375-3500; Sr. Elec. Foreman/ Elec. Foreman/ Traction Foreman in
Grade Rs. 2000-3200/- can record all measurements.
A 10% check by the Asstt. Elec.
Engineer/Divisional/district Elec. Engg. is necessary for the work costing upto
Rs. 25,000/- each if the value of the work exceeds the estimated cost by more
than 10% and for works costing above Rs. 25,000/- and 20% check by Asstt. Elec.
engineer/Divisional/District Elec. engineer is necessary.
(b) Asstt. Elec.Foreman/Asstt. Traction
Foreman/Sr. Elec.chargeman in grade Rs.1600-2660/- can also record the
measurements subject to 10% test check on the works costing upto Rs. 25,000/-
and 20% check on the works costing more than 25,000/- by Asstt. Elec. Engg./
Divisional/District Elec. Engineer.
(c) Elec. Chargemen/Asstt. Elec. Foreman in Gr.
Rs. 1400-2300 when they hold independent charge can record measurements for
works costing upto Rs. 25,000/- each subject to a test check by 20% by the
Asstt. Elec. Engg./Divisional/District Elec. engineer.
(d) Elec. Chargemen having a diploma in Elec.
Engg. and having more than three years of service and those not having a
diploma in Elec. Engg. but having six years experience nominated by name by the
Divisional/District Elec. Engineer can record measurements of works upto Rs.
10,000/- subject to a test check of 20% by the Asstt. Elec. Engineer/District
Elec. Engineer.
1316. On construction projects and special works, Sub-Overseer
Mistries cannot record measurements. Inspector of Works and Permanent Way
inspectors cannot record measurements for the supply of ballast, pitching
stones and earth work. For all other works, Inspectors of Works and Permanent
Way Inspectors in Grade I & II can record measurements upto a value of
Rupees One lakh, subject to a 20 per cent test check by the Assistant Engineer.
Measurement of ballast and pitching stones, classification of ballast and
measurement for earth work will be done by the Assistant Engineer.
1316A (Applicable for contracts wherein the measurement
of work by contractor is permitted): Para 1316 of Engineering Code shall not be applicable for
these contracts. For such contracts, contractor shall be responsible for
carrying out measurements of work executed and recording of measurements for
the release of on account/final payment. In such cases, the detailed procedure
for recording of measurements, provisional payment, test check and final
payment shall be as follows:
Contractor's Measurement Book:
1 Railway shall arrange contractor's
measurement book (CMB), each having sheet No, 1A to 4A(Form E 1313), followed
by 100 machine number pages (Form E 1313, sheet No, 5A). On the top of each
sheet of CMB, there shall be provision for recording the name of the work,
agreement number, name of contractor and CMB number.
2 CMBs shall be printed in such a way so
as to keep a clear margin of 50 mm on the left side of page, Further, the left
side shall have pinhole tear line at a distance of 15 mm from edge for ease of
taking out sheets from these books. The binding shall be within 15mm of the
margin available between edge and pinhole tear line. This shall ensure
availability of minimum 35 mm clear margin to re-bind measurement books later
on.
Movement and upkeep of Contractor's Measurement
Book:
3. Dy Chief Engineer in charge of contract (Dy
CE/C) shall hand over required No. of CMBs to Assistant/Executive Engineer
in-charge of contract (AEN/XEN) after taking receipt of the same on sheet No.
2A (Form E.1313) for further issuance to contractor time to time as per
progress of work.
4. CMB shall be registered with unique No. in
the Register of Measurement Books(Form E.1314) maintained In the office of Dy
CE/C. Separate accountal of CMBs for each agreement shall be maintained in the
office of Dy CE/C and AEN/XEN.
5. In case of change of 'contractor's authorized
engineer', fresh approval shall be taken from Dy.CE/C before recording of
measurement.
6. While issuing the CMB to contractor, AEN/XEN
shall take out sheet No. 2A to 4A from the CMB, take receipt of CMB from
contractor on sheet No. 3A (Form E.1313), and keep the same in safe custody.
7. Similar system as for CMB, shall be
followed for issuing Field Book/Level Book (E.1317/A) to contractor for
recording of levels in the field book/level book.
Measurement
8. The contractor's authorized engineer shall
record the measurements in CMB neatly in his own handwriting, without any use
of eraser/overwriting, without use of any typing fluid or any such thing. All
cuttings shall be initialed. No page shall be damaged /destroyed. No page shall
be kept blank in between the measurements.
9. The Contractor shall communicate the date of
measurement to AEN/XEN in sufficient advance' to witness any measurement.
Witnessing of measurement by railways is not compulsory except for initial
levels in case of earthwork and hidden measurements. Initial levels of
earthwork and hidden measurements are to be recorded in the presence of railway
officials and test checked as prescribed.
10. In oil account contract certificate,
measurement shall be recorded for the items and quantities to be paid in the
concerned on account contract certificate.
11. However, in every 4th on account contract
certificate and final contract certificate, the recording of measurement for
works executed shall include all the items and their quantity included in
previous on account contract certificates, irrespective of whether to be paid
or not in the current On Account Contract Certificate/Final Contract
Certificate.
12. No payment shall be processed on Lump
sum measurement taken by contractor's authorized engineer except for earthwork.
For earthwork, every 4th bill shall be based on actual levels taken and
detailed calculations carried out for the work done.
13. The contractor shall take out carefully from
CMB the used pages of CMB with one extra blank page for processing the bill;
staple them for submission to AEN/XEN along with bill, duly signing the
measurements. The contractor shall keep a photocopy of the measurements with
him for future reference.
14. At the time of submission of final bill, the
contractor shall submit all the remaining CMBs (unused as well as partially
used) with him along with bill to AEN/XEN.
15. The contractor shall submit required copies
of invoice and on account contract certificate/ final contract certificate
(similar to form E.1337 and E.1338) to the AEN/XEN duly marking them - original
or copy. Original shall he used for release of payment whereas duplicate copies
shall be used for record purpose in different offices.
16. In case contractor requires provisional
payment of on-account bill; the contractor shall submit his invoice and
provisional on account contract certificate for 75% of amount of work done
(before deduction of taxes). The contractor shall write 'For Provisional
payment ‘on top of such on-account contract certificate.
17. AEN/XEN while issuing receipt of stapled
sheets of CMB to contractor shall clearly record the same in sheet 4 (E.1314)
of concerned CMB, kept in the office of AEN/XEN.
Release of Provisional Payment
18. Senior Section Engineer / 'Junior Engineer
with 5 year experience' (SSE/JE) and AEN/XEN shall sign & record a
certificate on the original provisional 'on account contract certificate' as
under:
"Certified that the payment being made is
less than the amount due for the quantities of works executed by the
contractor".
In case of payment of earthwork items in any
contract, calculation of quantity of such items along with field book /level
book must be enclosed. This shall be cross checked, as considered appropriate
by SSE/JE & AEN/XEN, to ensure that no excess payment is being made. At
this stage no test check of measurements by railway is required.
19. AEN/XEN shall keep a copy of contractor's
invoice & provisional on account contract certificate in his office, and
submit original invoice & original provisional on account contract
certificate along with required number of duplicate copies, and used sheets of
CMB to the Dy CE/C unit for passing the bill and release of payment.
20. The provisional on account contract
certificate shall be passed by Dy CE/C and payment shall be released by
associate based on above certification of SSE/JE and AEN/XEN. After release of
payment, blank sheet of CMB (if any) shall be crossed by Dy CE/C before sending
the measurement sheets back to AEN/XEN for carrying out required test checks.
At this stage measurements shall not be crossed.
21. No provisional payment shall be allowed in
final contract certificate, Further, once provisional payment has been released
in any on-account contract certificate, the next on account contract
certificate can be raised by contractor only when accounts of previous on
account certificate (Provisional as well as remaining payment) has been
finalized,
Test Check
22. Necessary test checks shall be carried
out by the SSE/JE and AEN/XEN for the works done before full payment of
on-account contract certificate/final contract certificate, SSE/JE and AEN/XEN
shall communicate the date of test checks to contractor in advance. The
contractor can accompany during test check. The contractor shall provide
support staff and all required tools& plants to facilitate test check by
railway officials.
23. The stipulated test checks for AEN/XEN and
SSE/JE Level is tabulated as under:
S.NO. |
Description of works |
Test Check in terms of % of value
by |
|
SSE/JE |
AEN/XEN |
||
(a) |
Measurement of Ballast, pitching
stone, Earth work and hidden items. |
100% |
100% |
(b) |
Measurement of all other items. |
100% |
20% |
(c) |
Initial and Final levels along
centre line for earthwork in embankment and cutting. |
100% |
100% |
(d) |
Intermittent levels along centre
line for earthwork in embankment and cutting. |
100% |
20% |
(e) |
Initial, intermittent and final
levels except centre line for earth work in embankment and cutting. |
100% |
20% |
Note: The check regarding levels of
earthwork invariably shall be carried out in cross sections having heavy cross
slopes.
24. Contractor's recorded measurement sheets
shall be checked for any corrections/over writing during test check. All the
corrections/over writing shall be initialed by.SSE/JE.
25. The discrepancy noted (if any) during test
check of recorded measurement shall be communicated by AEN/XEN to the
contractor.
26. In case of discrepancy noticed during test
check, the contractor shall submit original and required copies of fresh
invoice of amount corrected for discrepancy, and in case provisional payment
has been released earlier, the required copies of fresh invoice of remaining
amount corrected for discrepancy (if any), along with on account/final contract
certificate to AEN/XEN.
Full payment of On Account Contract
Certificate/Final Contract Certificate
27. AEN/XEN shall submit original copy of
invoice and on account contract certificate of remaining amount/ Final Contract
along with required number of duplicate copies and used sheets of CMBs (all
used/blank CMBs in case of final contract certificate), duly signed by SSE/JE
and AEN/XEN to the Dy CE/C for passing the bill and release of payment.
28. Once the payment is released, Dy CE/C shall
return back the used sheets of CMB to AEN/XEN for safe custody. duly crossing
of measurements by finance officer.
29. Once all used of a particular CME is
received back by AEN/XEN from Dy CE/C, the AEN/XEN shall re-bind all 100 pages
of CMB along with sheet No. 1A to 4A for submission of CMB to Dy CE/C
office. Dy CE/C office shall record the receipt of same in sheet No. 2A
of CMB and Register of Measurement Books (Form E1314).
30. The final contract certificate shall be
passed by Dy CE/C only receipt of all CMBs (used/blank) from AEN/XEN.
31. The provisions of this para 1316A shall be
applicable to all the departments of Indian railways and to be executed through
equivalent authorities of respective departments.
1317. For measurement of earth work cross-sections levels may be
recorded by Inspector of Works in the field book which should be in ink or
inked before test checking by the Assistant Engineer. The Assistant Engineer
should exercise a check of 100 per cent in the case of levels along the centre
line of alignment, and not less than 20 per cent of the remaining levels of the
cross sections with the proviso that this check should invariably be carried
out in cross sections having cross slopes. All the corrections in the field
book must be initialed by the Assistant Engineer and no subsequent
corrections should be made by any person other than the Assistant Engineer who
while doing so should record the reasons for the same. The signature of the
contractor or his authorised agent should be taken on every field book accepting
the correctness of levels recorded therein.
Plotting of the cross sections may be done on graph paper taking care that
sufficiently large scale is adopted for plotting and there is not much
distortion of horizontal and vertical scales adopted. After plotting the cross
sections the levels should be inked and each sheet containing the cross section
should be signed by the Inspector of Works, Assistant Engineer and the
contractor. While plotting the cross sections, the proposed theoretical
profiles of the earth work should also be plotted to ensure that the work is
done to actual requirements and to avoid future claims from the contractors.
For computing the quantity of earth work arithmetical calculation is to be
preferred but if necessary counting of square method can also be adopted.
1317-A: The
field Books/Level Books used for recording the levels should be machine
numbered and these books should be maintained, accounted and kept in safe
custody in the same way as Measurement Books are maintained, accounted and
kept.
(Authority
Board’s letter No. 2007/ce.1/ct/8 dated 9-5-08)---ACS NO.44
1318. In the case of bridge girders and steel fabricated
structures the contractor can be permitted to submit his bill based on
completion drawings. These bills may be checked in the Drawing Office and
accepted for payment. No detailed measurements need be recorded in such case by
the Assistant Engineer in the measurement book.
1319. All measurement except as specified in paras 1317 and 1318
should be neatly taken down on the measurement book issued for the purpose and
nowhere else. For large works a separate measurement book may be set apart, or
if found convenient two or more books may be set apart for different classes of
works.
1320. Each set of measurements should commence with entries
stating :-
- (i)
In the case of work done :-
(a) Full name of work as given in the estimate;
(b) Situation of work;
(c) Name of contractor;
(d) Number and date of agreement entered into with contractor or of work order
issued in his favour;
(e) Dates of commencement and completion of work; and
(f) Date of measurement;
- (ii)
In the case of materials supplied :-
(a) Name of supplier;
(b) Number and date of agreement with supplier or of the order for supply;
(c) Purpose of supply;
(d) Dates of commencement and completion of supply; and
(e) Date of measurement;
and should end with the dated initials of the
person making the measurements. A suitable abstract should then be prepared
which should collect, in the case of measurements for work done the total
quantities of each distinct item of work relating to each sub-head of estimate.
1321. As all payments for work or supplies are based on the
quantities recorded in the measurement books, it is incumbent on the person
taking the measurements to record the quantities clearly and accurately. If the
measurements are taken in connection with a running contract account on which
work has been previously measured, the reference to the last set of measurement
should be recorded, and if the entire job or contract has been completed, the
fact should be recorded prominently and initialed by person taking the
measurements. If the measurements taken are the first set of measurements on a
running account, of the first and final measurements, this fact should be
suitably noted against the entries in the measurement book.
1322. Instructions for the Maintenance of Measurement Books.--The
pages of the book should be machine-numbered and no page should on any account
be torn out, nor should any entry be erased or deffaced so as to be illegible.
If mistake be made, it should be corrected by crossing out the incorrect words
or figures, and rewriting the correct words or figures, and the correction thus
made should be initialed. The entries must be made directly in the measurement
books at the site of work. The copying of entries from another rough note book
or similar record is strictly forbidden. A reliable record is the object to be
aimed at, as it may have to be produced as evidence in a Court of Law.
1323. The entries in the measurement book should, if possible be
made in ink, but when this is not possible, the entries should be recorded with
indelible or special copying pencil so as to render it difficult to tamper with
or to make unauthorised additions to or alterations in entries once made, the
pencil entries should not be inked over, but left untouched. The entries in the
"contents or area" column should, however, be invariably made in ink.
1324. Entries should be recorded continuously in the measurement
book. No blank pages should be left nor should any page be torn out, the
cancellation being attested. When any measurements are cancelled, the
cancellation should be supported by the dated initials of the officer ordering
the cancellation, or by a reference to his orders initialed by the officer who
made the measurement. In either case, the reason for cancellation should be
recorded.
1325. Each measurement book should be provided with an index which
should be kept up to date.
1326. From the measurement book, all quantities should be clearly
traceable into the documents on which payment are made, and a reference to the
voucher in which the quantities are entered for payment, as well as the date of
entry, should be given by an endorsement upon the original entries in the
measurement book, No contract certificate or bill should be signed without thus
crossing off the connected entry in the measurement book, and the document on
which payment is made should invariably bear a reference to the number and page
of the book in which the detailed measurement are recorded.
1327. Standard Measurements.-Detailed measurements may be
dispensed with in the case of periodical repairs when the quantities are
recorded in efficiently maintained Standard measurement books. In the case of
letting out the work of whitewashing of quarters on contract the Railways can
group the quarters in Division or Sub-Division Area in such a way that each
group includes quarters which would individually entrail approximately the same
equivalent surface area for whitewashing. The grouping should broadly be such
that all the quarters in one group should be susceptible of being given to one
contractor for the purpose of whitewashing. Non-standard bungalows of officers
may, however, be excluded from such grouping. The standard areas of white
washing to be paid for in respect of one unit of quarters in each group and
approximate number of units to be whitewashed should be clearly shown in the
tender documents. Payments should be made for the number of quarters actually
whitewashed on the basis of such area per unit as indicated in the tender
documents.
1328. Measurements based on Standard type Drawings.-Detailed measurements are not required in the
case of measurements of standard type staff quarters provided there is a
suitable clause in the agreement with the contractor to protect the railway
legally and the Assistant Engineer certifies that the work billed for has been
carried out in accordance with standard type drawings then the quantities as given
in the schedule of Estimates for standard type quarters for the type concerned
may be entered in measurement books for all work above floor level without
actual measurements being recorded.
For this purpose tenders for the construction of
buildings for which type designs have been prescribed should be invited at a
rate per unit of complete building. The detailed specifications and measurement
of the type of building should be fully given out in tender papers. Bills for
payment should be paid in terms of the number of buildings put up multiplied by
the rate approved per unit building. For regulating `on account' payments a
schedule of percentage payment due at various stage of construction of the
building e.g. up to sill level, up to ceiling level etc. should be included in
the tender documents. Where items not covered in the rate for the unit are
required to be provided, they should be separately shown in the tender
documents clearly bringing out what would constitute these "extras"
and how they would be measured and paid for. Similar provision should also be
made for any unforeseen items that may be required.
1329. This system may be extended with advantage to certain items
of repair work almost invariably done in complete units, such as colour washing
and oiling, varnishing or painting of doors provided that the Schedule of
Estimates for standard type drawings gives the quantities for these items
separately for each room, the rooms being distinguished on the drawing and in
the `estimate' by separate letters and also to the painting of bridges, tank,
tank staging and similar items which involves a very large number of entries,
if the work has been previously done and recorded in some extant measurement
book. In the latter case it should be sufficient to refer to the previous
measurement and merely enter total quantities for each bridge, tank, etc.
provided that the Assistant Engineer is able to certify that the quantity of
work done is the same as that of the previous measurement which will have to be
carefully filed under the Executive Engineers signature.
1330. Measurements for Lump-Sum Contract.-Detailed
measurements are not required in the case of a work done under a lump sum
contract. Final payment in such cases may be made on the certificate of the
Assistant Engineer to the effect that the work has been completed according to
the drawings and specifications.
1331. Approximate Measurements.-Detailed measurements may
dispensed with in cases in which payments `on account' for work actually
executed are made on the certificate of a responsible officer (not below the
rank of Assistant Engineer) to the effect that not less than the quantity of
work paid for has actually been done and that the measurement are from plans or
that they are approximately estimated. The officer granting such certificate
will be held personally responsible for any overpayments which may occur on the
work in consequence. Final payments should, however, in no case be made without
detailed measurements.
1332. Measurement of Ballast Train Work.-It is not usually
convenient to record in measurement books detailed measurement of work done by
contractors in connection with the working of ballast and material trains e. g.
loading and unloading of ballast, permanent way and other construction materials.
In such cases ballast train or material train challans in the following form
(E. 1332) should be prepared in four copies by the subordinate supervising the
loading of ballast or material. One copy should be retained as office copy of
the subordinate who trained out the material. Two copies should be sent to the
receiving subordinate through the guard of the ballast or material train. One
copy should be sent directly to the Assistant Engineer concerned immediately
after loading to reach within 24 hours to enable the Assistant Engineer to
verify the `ballast or materials if required. The receiving subordinate should
check the quantites of materials received with those shown on the challan and
accept it subject to any remarks he may have to make. One copy of the accepted
challan should then be submitted to the Assistant Engineer concerned to enable
the latter to prepare the contractor's loading and unloading bill. In this
case, the accepted challan takes the place of a measurement book.
1333. The
Measurement of Ballast.--Ballast should as
a rule, be measured in stacks. When ballast taken over by the Railway is
trained out, the correctness of the measurements recorded in the ballast train
challans, after making due allowance for shrinkage enroute should be checked
with the original stack measurements. In cases where owing to uneven surface of
the stacking ground or for want of space in the quarry, etc. ballast cannot be
stocked in stacks of convenient sizes and where in consequence ballast has to
be measured and taken directly in wagons, the procedure laid down in para 1332
may be adopted subject to a test check of 20% of the wagon measurements by the
Assistant Engineer.
1334. The
Divisional or Executive Officer should make it a point to see that the measurement
books are maintained in accordance with the rules laid down in paragraphs 1313
to 1332 ante and that the measurements recorded are complete records of each
kind of work done for which certificates have been given.
1335. Subject to
provisions of paragraph 1312 and 1327 to 1332 ante, the bills of contractors
for work done or supplies made should be prepared in any one of the following
forms according to that circumstances mentioned below against each :-
·
(i) Petty Contract
bill, Form E. 1336.
·
(ii) Running or On
Account bill, Form E. 1337.
·
(iii) Final Bill, Form
E. 1338. and
·
(iv) Hand Receipt,
Form E. 1339.
The final bill Form (E. 1338) should specifically provide
that the contractor concerned accepts the amount billed for as a final payment
in settlement of all his claims in respect of the particular work. Bill for
work done should necessarily be prepared in any one of the above forms. Bills
of supplies submitted on supplier's own forms may, however, be accepted when
prepared in English or Hindi, any further particulars required by the
departmental form being added by the disbursing officer. All bills passed
against a work order should be noted on the work order.
1336. The petty bill form (Form E. 1336) should be used for
making payments to contractors in connection with works or supplies when a
single payment is made for a job or contract on its completion. It may also be
used in paying several contractors employed on parts of one large work or
several works on one section of the line.
From E 1336 (Continued to........ List of
forms)
1337. The Running or Account bill from (Form E.1337
below ) is indicated for use in contract works only and not supplies. On
account payments before the completion of a work should be made through this
form.
Whenever there is any entry in
column 10 on the basis of actual measurements the whole of the amount
previously paid without detailed measurement should be adjusted by a minus
entry in column 2 equivalent to the amount shown in column 1, so that the total
up to date in column 3 may become nil.
When there are two or more entries
in column 10 relating to each sub-head of estimate they should in the case of
works the accounts of which are kept by Sub-heads, be totalled and the total
recorded in column 11 for posting the Register of Works.
1340. Preparation of Contractors Bills.-No fees should be
charged either for forms of bills supplied or for clerical assistance rendered
in the preparation of bills. A contractor requiring a copy of his contract
certificate or an extract from his account in the contractor's ledger (see
paragraph 1483) should be furnished with the same at a charge of Rs. 10/- which
should be credited to Government as a miscellaneous receipt under the head
"Receipts on Capital Account-Miscellaneous Receipts". In the case of
works charged to ordinary Revenue such receipts may be booked to Z-650.
No request from the contractor for supply of a copy of
contract certificate or an extract from his account in the ledger beyond a
period of six years from the date of closing of contract should be entertained
1341. In all
contractors' work and store bills the units calculation and rates should be
entered in words as well as figures. Whenever fraction of rupee occur in the
totals of contractors' bills fractions less than half may be disregarded and
half a rupee and over may be taken as rupee, before forwarding a contractor's
bill to the Accounts Officer for payment the Executive Engineer should satisfy
himself as to the correctness of the quantities billed, for the rates and all
recoveries.
1342. Other
Miscellaneous Payment.--Other payments
which an Executive Engineer has to arrange are with regard to pay, allowances
and other miscellaneous personal claims of the constructions staff such as
advances of pay, travelling allowances, withdrawals from P.F. etc. Such claims
should be dealt with in accordance with the rules and orders in the relevant
sections of the Indian Railway Codes.
1343. Bill for
Stores purchased.--This bill will be
prepared in Form S. 2817 which will be printed in English, Hindi and the
vernacular of the district in which used. Vendors of stores should be
encouraged to use these forms which may be supplied free of charge. In the case
of final payment on a running contract for the supply of stores, the same form,
but printed on yellow coloured paper, will be used, and disbursement made as on
final contract certificates. The procedure laid down in paragraph 739 of the
Indian Railway Code for the Stores Department should be followed in passing
claims for stores supplied.
1344. Pay Order.--This Form (E. 1344) is to be used only in the case of
such miscellaneous payments as refund of earnest money, payment of court
attachments., & Pay orders will be bound in books and will be
machine-numbered. These books will be issued on requisition only to those
officers who have been authorised by the General Manager to use them.
1345. General Rules.-Should any of the prescribed
forms not be used, care should be taken to see that no particulars, certificate
or signature required by the prescribed forms are omitted. The general rules
laid down in the following paragraphs should be observed in connection with the
claims referred to herein as "bills".
1346. Executive
Engineers submitting bill for payment should satisfy themselves that the same
are correct and complete in every particular and that sufficient authority
exists for their payment.
1347. All bills
be signed by the officer responsible for the outlay in token of his acceptance
of the claims, any alterations or corrections therein being duly initialed. In
the case of contractors' bill the signature of the contractor are also required
in token of their acceptance of the correctness of the bill submitted.
1348. A programme
should be drawn up by the Accounts Office fixing the dates for the submission
to it for check and payment of pay and allowance bill, muster sheets or labour
pay sheets and other claims of a recurring nature. In the submission of bills
executive officers should, except in emergent cases, adhere strictly to the dates
laid down in the programme in order to ensure punctual payment.
1349. Bill should
be dated and correctly allocated to the heads of accounts classification and
sub- heads of works concerned. In the case of bills chargeable to works, for
which estimates are sanctioned (see paragraph 701) the allocation should be
given in full detail as on the sanction estimates. This rule applies to all
vouchers, whether cash or adjustment and whether of open lines or of lines
under construction.
1350. In the case
of bill pertaining to Revenue working expenses, the month to which the bill is
debitable should be noted, as owing to the use of the head "Demands
Payable" it is, as a general rule practicable to adjust the liability
against the final head of account in the accounts of that month, even if the
payment may be made in the following month.
1351. No receipts
from the parties to whom the bill is payable should normally be taken in
anticipation of payment. The receipt of the payee should ordinarily be taken
upon the original passed bills or pay order. But when two or more bills or pay
orders are paid by a cheque, a receipt for the cheque should be treated as a
joint acknowledgement of payment of all the bills or pay orders, as the case
may be. The receipt should, however, give full particulars of all the bills or
pay orders in discharge of which the payment is made.
1352. No claims
of any class or description other than pay and other personal claims of
employees may be drawn in bills in the name of any servant of the railway.
1353. To
facilitate payments, the name of Pay District, the place of payment and the
name and designation of Witnessing Officers (if necessary) should be noted on
all bills and in the case of labourers, the name of the father of each payee in
addition to his own name should be entered in Labour Pay Sheets.
Check of Initial Records
1354. All initial records, whether of lines under
construction or of open line should, before they are presented for payment, be
checked to see--
·
(a) That they have been prepared in the prescribed forms
and that they are arithmetically correct;
·
(b) that the expenditure recorded has received the sanction
either special or general, of the authority competent to sanction it ;
·
(c) that the expenditure recorded has been incurred by an
officer competent to incur it ;
·
(d) that the expenditure does not involve a breach of any
of the canons of financial propriety.
·
(e) that the expenditure recorded is covered by provision
in the sanctioned budget allotment; and
·
(f) that the charge is correctly classified, and if a charge is
debitable to the personal account of contractor, employee or other individual
or is recoverable from him under any rule or order, it is so recorded on the
initial record and in prescribed account (where such account is kept by the
Executive Engineer).
1355. The
following subsidiary points require attention in the check of (i) muster sheets
and labour pay sheets and (ii) Contractors bills :-
(i) Muster Sheets and Labour Pay Sheets.--- It should be seen---
·
(a) that no classes of
establishment not properly chargeable to works vide paragraph 1121 have been
included therein;
·
(b) that the wages of
employees are charged at the rates sanctioned by the competent authority;
·
(c) that the wages charged for each gang or a group of labour
under each subordinate in the case of maintenance works do not without
sufficient reason (which should be investigated and recorded) vary materially
form month to month; and
·
(d) that the number, rates, period of employment and
total amount are within the sanction.
·
The check as regards
(c) above will be exercised in the Accounts Office through a manuscript
register called the gang register (Form E. 1354) wherein will be posted the
amounts of wages passed for payment every month for each gang or group of
labour.
(ii) Contractor's Bills.---It should be seen--
·
(a) that there are no delays in making measurements or in
preparing bills after the measurements have been taken;
·
(b) that rates higher than those provided in the
agreement or work order are not allowed without the specific sanction of the
competent authority;
·
(c) that
the running account and final bills are checked with the postings in the
contractor's ledger, form E. 1483;
·
(d) that recoveries have been correctly made according to rules
on account of materials issued against items of works for which labour and
material rates are paid;
·
(e) that for items for which labour, rates only are paid the
quantities of materials issued and charged finally to works are not excessive (
the cost of materials wasted in defective works subsequently rectified should
be recovered);
·
(f) that the quantities executed are according to the
sanctioned plans and estimates; and
·
(g) that the methods of measurement are correct.
Technical checks detailed as items (e) to (g) above should,
as a rule be exercised in the Drawing Office under the supervision of the
Executive Engineer.
Multiple choice questions:
1.What should be done if a
measurement book page contains a mistake?
- A. Erase the incorrect entry and rewrite it.
- B. Cross out the incorrect entry, rewrite the correct
entry, and initial the correction.
- C. Tear out the page and use a new one.
- D. Ignore the mistake as long as it is minor.
Answer: B. Cross out the incorrect entry, rewrite the correct
entry, and initial the correction.
2.When are detailed measurements
not required for work done under a contract?
- A. When work is done based on standard type drawings
and specified clauses.
- B. When measurements are recorded in a rough notebook.
- C. When the measurements are approximate.
- D. When work is done on a lump sum contract.
Answer: D. When work is done on a lump sum contract.
3.What is the proper procedure
for recording measurements in a measurement book?
- A. Use a pencil for all entries.
- B. Make entries in ink or indelible pencil, with pencil
entries left uninked.
- C. Record entries in a separate notebook and transfer
them later.
- D. Use different colored pens for different types of
work.
Answer: B. Make entries in ink or indelible pencil, with pencil
entries left uninked.
4.In which scenario are standard
measurements used rather than detailed measurements?
- A. For repair work involving small, unique items.
- B. For whitewashing of standard grouped quarters on
contract.
- C. For bespoke building designs.
- D. For complex, multi-phase construction projects.
Answer: B. For whitewashing of standard grouped quarters on
contract.
5.What should be done if a
measurement book page needs to be cancelled?
- A. Tear out the page and replace it with a new one.
- B. Cross out the entries, provide the reason for
cancellation, and initial it.
- C. Leave the page as is and note the cancellation in a
separate document.
- D. Rewrite the entries on a new page and discard the
old one.
Answer: B. Cross out the entries, provide the reason for
cancellation, and initial it.
6.For what purpose should each
measurement book be provided?
- A. To serve as a personal record for the individual
taking measurements.
- B. To include an index that should be kept up to date.
- C. To allow for free-form entries without any indexing.
- D. To summarize only the final measurements.
Answer: B. To include an index that should be kept up to date.
7.What action is required for
bills of supplies submitted on the supplier's own forms?
- A. They are automatically accepted without additional
requirements.
- B. They must be prepared in English or Hindi with
additional particulars as needed.
- C. They should be rejected unless in the official bill
format.
- D. They must be re-written in the departmental form.
Answer: B. They must be prepared in English or Hindi with
additional particulars as needed.
8.What should be done with
entries in a measurement book when the work is completed?
- A. Simply note that the work is completed.
- B. Record the fact prominently and initial it.
- C. Remove the page from the book.
- D. Transfer the entries to a different ledger.
Answer: B. Record the fact prominently and initial it.
9.In case of using a standard
type drawing for measurement, what should be done if no detailed measurements
are needed?
- A. Measurements should be made based on estimates from
the type drawings.
- B. The quantities should be recorded as per the
schedule of Estimates.
- C. All measurements should be taken on-site anyway.
- D. Detailed calculations are still required.
Answer: B. The quantities should be recorded as per the schedule of
Estimates.
10.What is the procedure if
ballast is measured and taken directly in wagons?
- A. Detailed measurements should be recorded in the
measurement book.
- B. Ballast train challans should be used, with a 20%
test check by the Assistant Engineer.
- C. The measurements are considered as final without
further checks.
- D. Only a summary of the measurements is needed.
Answer: B. Ballast train challans should be used, with a 20% test
check by the Assistant Engineer.
11.Which form should be used for
bills of stores purchased?
- A. Form E. 1344
- B. Form S. 2817
- C. Form E. 1336
- D. Form E. 1337
Answer: B. Form S. 2817
12.What should be done when an
Executive Engineer submits a bill for payment?
- A. Ensure the bill is signed by the vendor.
- B. Verify the bill's correctness and completeness and
ensure authority exists for the payment.
- C. Only initial any corrections on the bill.
- D. Submit the bill directly without verification.
Answer: B. Verify the bill's correctness and completeness and
ensure authority exists for the payment.
13.What action should be taken
when using Pay Orders for miscellaneous payments?
- A. Issue them in books that are bound and
machine-numbered.
- B. Use them only for payments related to pay and
allowances.
- C. Only use them for travel expenses.
- D. They should not be machine-numbered.
Answer: A. Issue them in books that are bound and machine-numbered.
14.Which of the following should
be avoided in the preparation of bills?
- A. Omitting required particulars or signatures.
- B. Using the prescribed forms correctly.
- C. Ensuring bills are signed and dated.
- D. Allocating bills correctly to account classifications.
Answer: A. Omitting required particulars or signatures.
15.What should be included in all
bills to facilitate payments?
- A. The name of the vendor only.
- B. Pay District, place of payment, and name and
designation of witnessing officers if necessary.
- C. Only the total amount and account code.
- D. The purpose of the payment only.
Answer: B. Pay District, place of payment, and name and designation
of witnessing officers if necessary.
16.When dealing with claims for
stores supplied, what form is used for final payment on a running contract?
- A. Form E. 1344 on yellow colored paper.
- B. Form S. 2817 on white paper.
- C. Form E. 1337.
- D. Form E. 1338.
Answer: A. Form E. 1344 on yellow colored paper.
17.What should be checked in the
initial records before payment?
- A. That the records are in chronological order.
- B. That the records are prepared in prescribed forms,
arithmetically correct, and sanctioned.
- C. That records are kept in alphabetical order.
- D. That expenditure is not related to any sanctioned
budget.
Answer: B. That the records are prepared in prescribed forms,
arithmetically correct, and sanctioned.
18.For which type of claims are
no receipts typically taken in anticipation of payment?
- A. Claims for materials.
- B. Claims for personal allowances and advances.
- C. Claims for administrative expenses.
- D. Claims for non-recurring repairs.
Answer: B. Claims for personal allowances and advances.
19.What should be done if a bill
is paid by cheque?
- A. No additional receipt is needed.
- B. A receipt for the cheque should be treated as joint
acknowledgment of payment for all bills or pay orders.
- C. The bill should be considered settled without any
receipt.
- D. The cheque should be returned if a receipt is not
available.
Answer: B. A receipt for the cheque should be treated as joint
acknowledgment of payment for all bills or pay orders.
20.What should be verified in the
case of contractors’ bills regarding measurements?
- A. Ensure no delays in measurements or bill
preparation.
- B. Confirm that measurements are only approximate.
- C. Check that the measurements are not based on
estimates.
- D. Ensure no need for verification against contractor’s
ledger.
Answer: A. Ensure no delays in measurements or bill preparation.
21.What should be noted on bills
pertaining to Revenue working expenses?
- A. The final approval of the expenditure.
- B. The month to which the bill is debitable.
- C. The exact amount spent.
- D. The purpose of each expenditure.
Answer: B. The month to which the bill is debitable.
22.Which records require a check
to ensure that expenditures are covered by the sanctioned budget?
- A. Only personal expense records.
- B. Initial records, whether for open lines or under
construction.
- C. Records related to administrative expenses only.
- D. Records for non-recurring payments.
Answer: B. Initial records, whether for open lines or under
construction.
23.What should be ensured
regarding labour pay sheets?
- A. That wages are charged at rates sanctioned by the
competent authority.
- B. That wages vary according to the time of month.
- C. That the total amount is left unverified.
- D. That wages are not recorded.
Answer: A. That wages are charged at rates sanctioned by the
competent authority.
24.What additional information
should be included in labour pay sheets besides the payee's name?
- A. The payee's contact number.
- B. The name of the payee's father.
- C. The payee’s home address.
- D. The payee’s job title.
Answer: B. The name of the payee's father.
25.In checking contractors'
bills, what should be done regarding the quantities executed?
- A. Ensure they are according to sanctioned plans and
estimates.
- B. Ignore discrepancies if they are minor.
- C. Verify only the final quantities.
- D. Recalculate quantities without referring to the
plans.
Answer: A. Ensure they are according to sanctioned plans and
estimates.
Comments
Post a Comment