Indian Railway Codes and Manuals-Engineering code-Chapter- 12 (XII)
CHAPTER
XII
CONTRACTS
FOR WORKS
I. Awarding of Contracts
1201. Definition of Contract.--When two or more persons have a common intention
communicated to each other to create some obligation between them there is said
to be an agreement. "An agreement" which is enforceable by law is a
"Contract" . According to Section 10 of the Indian Contract Act, 1872
only those agreements are enforceable by law which are made by the free consent
of the parties (see para 1256), competent to contract (see para 1259), for a
lawful consideration (see para 1224) and with a lawful object, and are not
expressly declared to be void. This is subject to any special law according to
which a contract should be in writing and attested by witnesses.
1202. Agency of Contractor.-The agency of contractors may, if economical or
expedient be utilized for the proper execution of works of construction,
repairs or maintenance on lines under construction and on open lines. Materials
which are in short supply or materials requiring test certificates for quality
control like cement, steel etc. may be supplied to the contractors by the
Railway, the agency of the Stores or other departments of the Railway being
utilized for the purpose vide paragraphs 701-S and 702-S. In exceptional or
urgent circumstances, however, e.g., with a view to the expeditious execution
of an urgent work, the Chief Engineer in the exercise of his personal
discretion, after consultation with his Financial Adviser and for reasons to be
recorded, may arrange for the supply or manufacture of materials required for
the work, through a contractor.
1203. Works Contracts.-All works and supplies relating to the
Engineering Department executed through the agency of contractors may be
broadly classed as follows :
(i) Zone Works.-Such
as works of ordinary repairs and maintenance and others of petty nature in a
particular zone, or area;
(ii) Special
Works.-Such as the construction of bridge, the formation of an embankment
etc. other than zone works;
(iii) Supplies
of building materials.-Such as bricks, tiles, lime, bamboos, ballies,
matting, doors, windows, ballast, boulders, moorum, stone chips, fire bricks,
shingle, pitching stone etc. which are not usually stocked or purchased by the
Stores Department.
Contracts relating to
these three classes will for the purpose of this Code be termed as `Work
Contracts' as distinguished from `Stores Contracts' which pertain to the supply
of stores arranged by the Stores Department.
1204. Forms of Works Contracts.-The following forms of contract are primarily
intended for application to Works Contracts (c. f. para 408-S) :
- (i) Lumpsum contract :
- (ii) Schedule contract; and
- (iii) Piece work contracts.
1205. "Lumpsum" Contracts.-The Lumpsum Contract is a contract under which
the contractor engages to carry out a work or effect supply as specified and
within a given period for a fixed total sum; his receipt of this sum being
dependent on his completing the work or supply to specification and time,
irrespective of the actual quantities and kinds of work done of materials
supplied in achieving his results (c. f. para 403-S).
1206. In the case of such contracts a scale of rates or prices may
be agreed upon by which enhancement of or reduction from the lumpsum may be
regulated in the event of any departures from the work or supply as specified
being made subsequently under the order of competent authority; or by which
reductions may be made, at the discretion of competent authority for failure on
the contractor's part to conform to specification. (c. f. paras 1328 and
404-S).
1207. Schedule Contract.-The Schedule Contract is a contract under which
the contractor engages to carry out a work or effect supply as specified and
within a given period, at fixed unit rates or prices for each of the various
items comprising such work or supply, the sum he is to receive depending on the
actual quantities and kinds of work done or materials supplied in completing
the work or supply to specification and time. It is not repugnant to the above
definition to show in such contracts the approximate amount of the contract,
based on approximate quantities and the fixed unit rates. (c.f. para 405-S).
1208. Piece Work Contract.-This means a contract under which only unit
rates or prices for various kinds of work or materials are agreed upon, without
reference either to the total quantity of work to be done or materials
supplied; or to the quantity of work to be done or material supplied within a
given period. The Zonal Contract adopted on the Railways (refer para 1209) fall
under this category (c.f. para 406-S).
Note.- Agreeable to the
above definition of a piece work contract.-(a) the Railway may indicate its
intention as to the maximum value of the orders it is likely to place; but the
contractor cannot claim to be given an order for more than one unit of work or
supply; (b) after the contract is executed, specific orders for work or supply
may be placed against it; and (c) rate of progress may not be specified; but if
it is not satisfactory the contract can be terminated.
1209: Contracts for zone works and Engineering Materials- It is often
advantageous to allot all minor works and all works of repairs and maintenance
in a particular zone for a definite period to one contractor. It may be
likewise advantageous to make this contractor who can be called It zonal
contractor responsible for the conveyance or supply of engineering materials as
and when required, in a particular zone during a specified period, The
Executive Officers of the Engineering Department should therefore, take steps to
select suitable contractors for zone contracts which will include:
i. New Works, additions and alterations to
existing structures, special repair works and supply of building materials
subject to the contract value of each such work not exceeding Rs 5 lakh,
ii. All ordinary repairs and maintenance works;
and
iii. Conveyance of materials e.g, bricks, lime,
sand etc, which are likely to be required in a Zone during the year.
The zonal contracts
should be for the period from 1st of July to 30th of June, The contracts for
these works or supplies should as a rule, be on a yearly basis, If, however,
any special advantage, such as more favorable rate is likely to be secured
giving out contracts for longer periods in the case of manufacture or supply of
bricks) contracts for more than a year may, with the concurrence of the
Accounts Officer, be entered into, it should be ensured that as far as
practicable, no work orders are approved the old contract after the opening of
the new tenders and all works of the old contract are completed by the end of
June. Exceptional cases may, however, be dealt on their merits with the
approval of the competent authority, taking into account all relevant facts
including such information as is available regarding the trend in rates.
1210. Tender System.-It is the primary duty of the Executive to
obtain the best value possible for the money spent and the tender system should
be given a very careful and serious consideration in all cases as one of the
most effective methods of securing competitive rates. The exceptions made to
the general rule, that the tenders should be called for, in all cases are based
only on practical considerations in order to avoid delay and unnecessary work
in the cases of works of comparatively small value. (c.f. para 323-S and
602-F).
1211. Circumstances when tenders need not be called
for.-Except where for
reasons which should be in public interest the General Manager decides that it
is not practicable or advantageous to call for tenders, all contracts over Rs.25,000/-
in value should be placed after tenders have been called for in the most open
and public manner possible and with adequate notice. For works contracts based
on Schedule of Rates in force on the Railway, calling of tenders up to Rs.
50,000/- can be dispensed with by the General Manager without recording reasons
for doing so. In all other cases where it is decided not to call for tenders,
the reasons should be recorded and financial concurrence obtained.
Should the General
Manager's powers of decision under the preceding sub-para be delegated to a
lower authority (who will exercise it subject to the same proviso) and should
the Account Officer consider the reasons adduced by such authority to be
insufficient or other than in public interest, he should represent his views to
the higher authority concerned and, if necessary, consult the General
Manager."
Note :-General Manager
may delegate powers to dispense with calling of tenders for works
uptoRs.50,000/- each in value in consultation with the Associate Finance at the
stage of acceptance of offer, subject to the following stipulations :-
- (i) Normally powers to despense with calling of tenders
should be exercised sparingly. However, in special cases, where it is felt
necessary to do so, reasons for taking such decision should be recorded by
the competent authority in each case viz. JA Grade officer upto Rs.
40,000/- each and Senior Admn. Grade Officer upto Rs. 50,000/- each
subject to an annual limit of Rs. 4,00,000/- per officer.
- (ii) The work should not be split up for the purpose of
bringing it within the ambit of this dispensation.
- (iii) The reasonableness of rates should be gone into
objectively by the accepting authority.
- (iv) Quotations should not be for items which can be
executed through the existing contracts including zonal contracts;
- (v) Quotations should not be for fancy (expensive but
of low utility) items;
- (vi) Quotations should only be for works which are
urgent in nature.
- (vii) Quotations should normally be invited from at
least 3 contractors working in that area. At least two of them should be
from the approved list of the Division.
- (viii) Accepting Authority must take precautions to see
that the quotations are from genuine firms (and not from fictitious
firms); and
- (ix) A Register showing full particulars of works
authorised will be maintained by each officer and this should be open to
verification by Accounts while passing the bills. DRM/ADRM should have a
monthly review as a matter of control.
1212. Classes of Tenders.-The following are amongst the different methods
of obtaining tenders that may be adopted :-
- (i) By advertisement ("Open" tenders);
- (ii) By direct invitation to a limited number of
firms/contractors ("Limited" tenders); and
- (iii) By invitation to one firm/contractor only ("Single"
tenders). (c.f. para 323-S and 603-F).
1213. Open Tender System :-The system of invitation to tender by public
advertisement in the most open public manner possible should be used as a
general rule and must be adopted, subject to the exceptions noted in paragraphs
1211 and 1214.
1214. Limited Tender System :-
(i) Where for reasons
which should be in the public interest, it is considered not practical or
advantageous to call for open tenders, limited tenders may be invited with the
concurrence of the Financial Adviser and Chief Accounts Officer and approval of
the competent authority. The reasons for inviting limited tenders from
firms/contractors should be kept on record while approaching finance for
concurrence.
(ii) In open line
railways, the systems of inviting tenders for works costing up to Rs. 40 lakhs
(Rupees Forty lakhs) each from amongst the contractors borne on the approved
list may also be adopted when it is considered advantageous to do so, provided
the number of contractors borne on the approved list for the particular type of
work is not less than 10.
(iii) Some percentage of
the tenders which would normally be finalised by calling limited tenders, be
finalised by calling open tenders so as to test the market rates periodically.
(iv) Notice for `Limited
Tenders be sent to all eligible contractors borne on the approved list.
Note :-Notwithstanding
the provision contained in para 1214 (ii) above, the Railways may invite open
tenders in the following circumstances :-
- (a) In the event of insufficient response to the tender
from the contractors borne on the approved list;
- (b) When the work is of special nature and contractors
with requisite experience are not available on the approved list; and
- (c) When ring formation is suspected."
1214-A Single tender can be awarded under
following situation such as :
(1) EMERGENT
SITUATION :
- (a) Accidents, breaches involving dislocation to
traffic.
- (b) Works of specialised nature to be personally
approved by the GM/CAO (C) with prior/ concurrence of the FA & CAO.
This power is not to be delegated to any other authority.
- (c) Any other situation where General Manager
personally considers it inescapable to call for single tenders subject to
this powers can be exercised by GM only with prior concurrence of Finance.
(2) Annual
Maintenance Contract for equipment can be placed on single tender
basis on authorised dealers with approval of Additional General Managers of
Railways.
NOTE.--These powers may
be delegated by the General Managers in consultation with FA & CAOs to
PHODs/DRMs upto a maximum of Rs. 5 lakhs per item per annum. On re-delegation,
these powers would be exercised by PHODs/DRMs in consultation with associate
finance.
1215. List of Approved Contractors :-No work or supply should ordinarily be
entrusted, for execution, to a contractor whose capability and financial status
has not been investigated beforehand and found satisfactory. For this purpose,
a list of approved contractors may be maintained in the headquarters and
Divisional Offices of the Railway. Other contractors who have done satisfactory
work on the Railways or outside the Railways may be added to the list, in
consultation with the Financial Adviser and Chief Accounts Officer, or
Divisional Accounts Officer.
1216. The list of approved contractors be
prepared and maintained in Headquarter and Divisional offices of Railway, where
the intending contractors would undertake to execute Railway works, by
observing the under-noted procedure.
(i) Once a year, by
giving wide publicity through advertisements etc., intending contractors may be
invited to register themselves for different classes. Contractors already on
the "Approved List" and those who have executed/done satisfactory
work on the railways, thereby qualifying themselves to be relied upon for allotment
of works/assignments in future, should also be invited to get themselves
registered.
(ii) The basic
requirements for registration as circulated vide Board's letter No.
85/W.I/CT/23- GCC dated 31-1 86 should be spelt out and made well known in order
to reduce discretion and arbitrariness in the selection for registration.
(iii) Where required,
capacity of the intending contractors to execute works satisfactorily as an
independent and competent agency, their financial capability for satisfactory execution
of railway works, field of specialisation, past experience, ability to
supervise the works personally or through competent and qualified/authorised
engineers/supervisors, be examined and investigated expeditiously prior to
their enlistment.
(iv) An annual fee of
Rs. 1,000/- should be charged from such registered contractors to cover the
cost of sending notices to them and clerkage for tenders etc.
(v) The selection of
Contractors for enlistment in the "Approved List" should be done by a
Committee for different value slabs, and accepted by the Accepting authority.
The composition of the Committee and the authority for acceptance shall be as
prescribed by the Railway Board from time to time.
(vi) The "List of
Approved Contractors" be treated as confidential office record and
individual names of contractors on the list should not be made known to other
contractors. It should be maintained upto date in a neat and unambiguous
manner.
1217. Principles to be observed in framing contract
agreements.-The basic principles
to be kept in view by those who are authorized to enter into contracts or
agreements are given below :-
(i) The terms of
contract must be precise and definite, and there should be no room for
ambiguity or misconstruction and matters to be agreed upon should include, in
detail, the following :-
- (a) What the contractor is to do; when, where and to
whose satisfaction it is to be done;
- (b) What the railway administration is to do; and on
what terms;
- (c) What payment is to be made; what it is to cover, to
whom it is to be made, and the method and basis of making it;
- (d) the responsibility of the contractor in respect of
adequate supervision, care of Government property, and the protection of
outside interest and those of the staff and workmen;
- (e) the terms on which variations and modifications, if
any, are to be permitted; and authority competent to order and assess
them, and the occasion and basis of such assessment;
- (f) the measures to be adopted in the event of a
breach, of the contract by either party thereto; and the correct method of
and the grounds for determination therof;
- (g) the method of settling disputes.
(ii) As far as possible,
legal and financial advice should be taken in the drafting of contracts before
they are finally entered into.
(iii) Standard froms of
contract should be adopted wherever possible, the terms to be subject to
adequate prior scrutiny.
(iv) The terms of
contract once entered into should not be materially varied except in
consultation with the competent legal and financial authority.
(v) No contract
involving an uncertain or indefinite liability or any condition of an unusual
character should be entered into without the previous consent of the competent
legal and financial authority.
(vi) Provision must be
made in contracts for safeguarding Government properties entrusted to a
contractor.
(vii) In entering into
long term agreements or contracts, consideration should be given to the
desirability of providing for the railway administration unconditional power to
cancel the agreement at any time after the expiry of six months notice to that
effect.
(viii) The power to
retain and "set off" all claims whether arising out of the particular
contract or out of any other transaction or claim whatever against the
contractor should be secured for the railway administration. (c.f. para 626 F
and 402 S).
1218. Documents forming integral part of contracts.-The documents forming integral parts of a
contract are the conditions of contract, standard or special; the
specifications, standard or special (and any plans necessary) the schedule of
items, quantities and rates; the agreement form; instructions to tenderers; and
tender forms (if any). (c.f. paras 630 F and 416 S).
1219. Specification and drawings.-The execution of works and supply of materials
on contract should be according to standard specifications and drawings,
whenever possible rather than to sample. If no standard specifications exist
for any item or work or supply, a complete specification of the item and of the
materials to be used should be prepared and embodied to the contract documents.
For special works, complete sets of drawings showing the general dimensions of
the proposed work, and if need be, details of the various parts should be
prepared and made available for reference by intending tenderers.
1220. Conditions of Contract-The conditions of contract may be either
standard or special. The standard conditions of contract are prescribed by the
Railway Board. In additional special conditions may be prescribed when considered
necessary. (c.f. para 631 F and 417 S).
1221. Use of standard conditions.-Standard conditions are preferably embodied in
all contracts to which they are applicable. In the event of such conditions
proving defective in any way, it will be the duty of the General Manager to
report the fact to the Railway Board, if such conditions were prescribed by
them, and in all others cases to arrange, in consultation with his Legal and
Financial Advisers, to amend or amplify them suitably. (c.f. para 631 F and 418
S).
1222. Unusual conditions-Any unusual conditions of contract should,
before they are imposed, be approved by the General Manager, acting in
consultation with his Legal and financial Advisers or if the contract to which
they relate is beyond his powers to execute, by the Railway Board, (c.f. paras
632 F and 419 S).
1223. The interpretation to be placed on the
word "unusual" is left to the General Manager who will use his
discretion both in issuing instructions as to the cases to be submitted to him
and also in deciding which cases should be referred to the Railway Board. (c.f.
para 420 S).
1224. Lawful consideration.-For a contract to be legal, there must be a
"Lawful consideration" for performance. Such
"consideration" may take a positive form (i.e. an agreement to order
a certain quantity of work or materials) or a negative form (i.e. an agreement
not to order certain work or materials from any one but the contractor). The negative
form of "consideration" may be advantageously employed in cases of
the supply of materials of a perishable nature or which is not necessary to
store, or for the requirement of which is not possible to estimate; or for
where a contractor offers to carry out all works on a division at a fixed
percentage below schedule of rates. (c.f. para 422 S).
1225. If time is to be "of the essence" of a contract it
should be specifically so stated. It may in some cases be found advisable to
avoid `Penalty Clauses' by lowering the basic rate and providing for an
enhanced rate which would bring it up to standard, if the contract is completed
by the time specified. A penalty clause of any nature is, in any case
pre-eminently a matter on which legal advice should be obtained. (c.f. para 423
S).
1226. Issue of Railway materials.-Where Railway materials are to be utilized
and, for valid reasons net (i.e. labour) rates are not employed, the rate at
which the value of such material will be recovered together with the place or
places at which they will be delivered should be detailed. It should be made
clear that all lead and lift from that place to the site of work would be at
the expense of the contractor.
1227. Issue of tools and plant to contractors.-Where tools, plants, patterns or other Railway
property are lent to a contractor for the performance of his contract, the
terms of such loan should clearly be specified. In order to safeguard Railway
property adequately, it is desirable that in addition to providing that any
damage or deterioration is made good, a provision should exist that the
contractor is responsible for `loss or destruction'. Under the Law of Bailment
the contractor, in the absence of any special contract is not responsible for
loss, destruction or deterioration, if he has taken the amount of care that a
man of ordinary prudence, would under similar circumstances take of his good'.
(c.f. para 425 S).
1228. Special conditions should not be tacked on
to standard conditions until the effect of doing so has been carefully examined
and consequential changes carried out. (c.f. para 427 S).
1229. One of the conditions if the contract
should be that any gift or offer of illegal gratification made by the
contractors or others on his behalf renders the contract void. (c.f. para 428
S).
1230. Rates.-All rates should be entered in a contract, in words as well as
in figures and what they are to cover, should be clearly stated in the
contract. (c.f. para 432 S).
1231. Subject to any general or specific order
at the time being force the authority empowered to execute a contract is
competent to decide on the rates therefor; provided that where such rates are
in excess of the market or standard rates or the Railway, or rates quoted by
railway workshops for the manufacture of the stores in question, the authority
should record the reasons for adopting the higher rates. (c.f. para 433 S).
1232. Quantities.-All quantities should be entered in a contract in words as well
as in figures. (c.f. para 434 S).
1233. Nomenclature.-As far as practicable standard forms of
nomenclature or description should be employed, the terminology should be such
in all cases as to show beyond all reasonable doubt what exactly is required.
(c.f. para 435 S).
1234. The right should invariably be preserved
to reject any or all of the tenders received without the assignment of reasons.
1235. Tender Forms.-Tender Forms supplied to tenderers should
completely embody either directly or by reference the contents of the contract
documents. In the event of there being any discrepancy between the two it
should specifically be stated in the former as to which will prevail. Tender
forms should inter-alia state:
- (a) the amount of earnest money to accompany the tender
and the nature of security deposit, if any, required in the case of an
accepted tender;
- (b) with whom or what authority, the acceptance of a
tender will rest; and
- (c) whether or not tenders containing erasures and
alterations of the tender documents will be considered.
Note.-Such alterations
constitute fresh proposals and cannot be disregarded, but must definitely be
accepted or rejected. All tenders should, therefore, in equity be placed on the
same footing in this respect.
1236. Tenders involving foreign exchange.-In cases of tenders involving foreign exchange
expenditure in excess of Rs. 50,000, prior reference to the Board shall be made
for their approval, before tenders are called for. (c.f. para 604 F).
1237. Before the Railway Administration enter
into any contractual arrangements involving payment or provision by the
contractor of equipment like pneumatic set or other similar costly equipment as
a stand-by, the orders of the Railway Board should be obtained.
1238: Tender Notice- Sufficient notice should be
given for the submission of tenders, which in the case of large works should
not be less than a month. The above prescribed tender notice period may be
departed from in the most exceptional circumstances only and then too in
consultation with the Principal Financial Adviser.
However:
(i) For
tenders valued upto and including Rs 1 crore invited through e-tendering, the
tender notice period can be reduced upto 21 days by CAO/DRM without finance
concurrence and upto 14 days with the concurrence of Associate Finance.
(ii) For
tenders valued above Rs 1 crore and upto & including Rs 2 crore invited
through e-tendering, the tender notice period can be reduced upto 14 days by
CAO/DRM with the concurrence of Associate Finance.
1239. The tender notice should in all case state
:-
- (i) the place and time where contract documents can be
seen.
- (ii) the place and time where blank tenders forms can
be obtained.
- (iii) the amount, if any, to be paid for such
documents.
- (iv) the place, where, the date on which and the time
when tenders are to be submitted and are to be opened.
1240. Sale of tender forms.-When open tender system is adopted the issue of
tender forms need not be restricted to contractors, whose names are in the
approved list. Contractors not on the approved list may on payment of the
prescribed fees be furnished with tender forms and allowed to tender for the
advertised requirements.
1240 A. Cost of Tender
Forms. The Cost of Tender Form
shall be as under :-
) For works costing upto Rs. 5
lakhs. |
Rs. 1000/- |
(ii) For works costing above Rs. 5
Lakhs and upto 20 lakhs. |
Rs. 2000/- |
(iii) For works costing above Rs.
20 Lakhs and upto 50 Lakhs. |
Rs. 3000/- |
(iv) For works costing above Rs.
50 Lakhs and upto Rs. 2
crores . |
Rs. 5000/- |
(v) For works costing above Rs. 2
crores and upto Rs. 50 crores. |
Rs. 10000/- |
(vi) For works costing above Rs.
50 crores |
Rs. 25000/- |
Note:
Apart from above:-
(i) |
If any plan/ drawing is attached
with the Tender Form, Rs.200/- per plan/ drawing will be levied extra. |
(ii) |
If any Tender Form is to be sent
by Regd. Post, additional Postal Expenses @Rs.500/- per Tender Form
will be changed. |
(Authority Board's letter No.
94/CE.I/CT/53 dated 25.07.94 & 18.5.07)
1241. Earnest Money.-The amount of earnest money deposited should be
sufficiently large to be a security against loss, in event of the contractor
failing to undertake the contract or to furnish the required security within
the appointed time after the acceptance of his tender or until such time as the
sums due to him form a sufficient guarantee, as the case may be.
1242. The amount of earnest money required to be
deposited with the tenders as initial security shall be as under :-
(i) |
For works costing upto Rs. 5 lakhs. |
2 ½% ad valorem subject to a maximum of Rs. 10,000/- |
(ii) |
For works costing more than Rs. 5 lakhs but upto Rs. 20
lakhs. |
2% ad valorem subject to a maximum of Rs. 20,000/- |
(iii) |
For works above Rs. 20 lakhs but upto Rs. 50 lakhs. |
1% ad valorem subject to a maximum of Rs. 35,000/- |
(iv) |
For works above Rs. 50 lakhs. |
¾% ad valorem subject to a maximum of Rs. 50,000/- |
.In case the tenderer
withdraws his offer within the validity date of his offer or fails to undertake
the contract after acceptance of his tender. The full Earnest Money should be
forfeited. Earnest money in the form of Guarantee Bonds should not be accepted.
1243. The Railway Administration may, however,
at their discretion fix a lower or higher percentage and or the maximum amount
of earnest money for any individual work in consultation with their Financial
Adviser and Chief Accounts Officer, keeping in view the value and nature of the
work and also ensuring that provisions of para 1241 are followed.
1/5th of the amount
indicated in para 1242 should be notified and collected as a security deposit
for the due performance of the stipulation to keep the offer open till such
date as may be specified in the tender. The tenderer after submitting his
tender will not resile from his offer or modify the terms and conditions. If
the tenderer fails to observe or comply with the stipulation, the amount
indicated aforesaid shall be forfeited by the Railway.
The balance 4/5th amount
should be notified and recovered as a part of earnest money along with the
amount indicated in sub-para above, which together constitutes the earnest
money. If the tender is accepted this earnest money will be retained by the
Railway as a part of security for due and faithful fulfillment of the contract.
1244. Security Deposit.-Security deposits are to be paid by contractor
in token for the due fulfillment of a contract. The amount of security deposit
required will be as under :--
(i) |
for contracts upto Rs.1 lakh in
value |
10% of the value of the contract |
(ii) |
for contracts costing more than
Rs. 1 lakh upto Rs.2 lakhs in value |
10% of the first Rs.1 lakhs and 7½% of the balance |
(iii) |
For contracts more than Rs.2
lakhs and upto Rs.2 crores. |
10% of the first Rs.1 lakhs , 7½% of the next
Rs.1 lakhs and 5% of the balance subject to the maximum of Rs. 10
lakhs. The amount over and above Rs.3 lakhs. to be recovered from the
progressive bills of the contractors at the rate of 10% till it reaches
the required value. (Authority: Railway Board letter
No.88/CE-I/CT/1 ((Vol.II) dated 1-11-02) |
(iv) |
For contracts above Rs.
2 crores . |
5% of the contract value. The amount over and above Rs.3
lakhs to be recovered from the progressive bills of the contractors @ 10%
till it reaches 5%. Of the contract value |
In special cases where a
reduction in security deposit may enable the Railway to obtain a more
favourable rate, the percentage of security may be reduced or a suitable
lumpsum, as considered necessary, be fixed by the General Manager in
consultation with his Financial Adviser and Chief Accounts Officer.
The security deposit may
be collected by deduction from running bills of the contractor at the rates
mentioned in sub-para above. The total security recovered from a contractor
including the amount of the earnest money should not exceed the security amount
recoverable at the rates mentioned in sub-para above. This does not, however,
preclude the contractor from depositing the security money either in cash or in
other accepted forms of payment.
1245. Standing Earnest Money.-A standing earnest money of the values indicated
below can be accepted from a contractor borne on the Railway list of approved
contractors to cover tendering against any number of works costing upto the
limit indicated against each amount on the Zonal Railway Civil Engineering
Department:--
(i) |
Upto Rs. 5 lakhs |
Rs. 10,000/- |
(ii) |
More than Rs. 5 lakhs but less
than Rs. 20 lakhs. |
Rs. 20,000/- |
(iii) |
More than Rs. 20 lakhs but less
than Rs. 50 lakhs. |
Rs. 50,000/- |
(iv) |
More than Rs. 50 lakhs. |
Rs. 1,00,000/- |
This amount would not be
adjustable towards the security deposit of individual contracts obtained by a
contractor.
1246. Forms in which earnest money and security
deposit is acceptable.-The
earnest money should be in cash or in the form of deposit receipts, pay orders,
demand drafts or guarantee bonds executed by State Bank of India of any of the
nationalised bank or by a scheduled bank. Government Securities (Stock
Certificates, Bearer Bonds, Promissory Notes, Cash Certificates etc.) should
not be accepted as earnest money. The proviso regarding earnest money does not
apply to other railways or departments of Government.
The security deposit may
be in the following forms :--
- (i) a deposit of cash;
- (ii) Government securities including State Loan Bonds
at 5 per cent below the market value;
- (iii) deposit receipts pay orders, demand drafts and
guarantee bonds. These forms of security deposit could be either of the
State Bank of India or of any of the nationalized banks;
- (iv) guarantee bonds executed or deposits receipts
tendered by all scheduled banks;
- (v) a deposit in the Post Office Saving Bank;
- (vi) a deposit in the National Savings Certificates;
- (vii) twelve years National Defence Certificates;
- (viii) ten years Defence Deposits;
- (ix) National Defence Bonds; and
- (x) Unit Trust Certificates at 5 per cent below market
value or at the face value whichever is less. (c. f. para 1801 A).
1247. Tenders received by Post.-Tenders received by post should be entered in
the Tender Register and the time of receipt should be recorded on the cover of
the tender and deposited before the closing time in the tender box.
1248. Opening of Tenders.-Tenders should be opened at the specified time,
date and place by the Officer nominated for this purpose. The presence of an
Accounts representative at the time of opening of tenders is required, if the
tender value is above Rs. 10,000 in the presence of the intending tenderers.
(c. f. 607 F).
1249. Precautions to be observed while opening the
tenders.-The Officer who opens
the tenders and the Accounts representative witnessing the tender opening
should :
- (i) Initial (with date) the cover containing the
tender, front cover page of the tender and every page of the tender on
which the rates or special tender conditions are quoted;
- (ii) Initial (with date) all corrections in the
schedule of quantities, schedule of materials to be issued and
specification and other essential parts of the contract document;
- (iii) Mark and initial all over writings in red ink.
The corrections, overwritings and omissions should be serially numbered
and the total number of such corrections etc. should be clearly mentioned
at the end of each page of the schedule attached to the tender proper and
attested with date;
- (iv) Clearly indicate on each page of the schedule
attached to the tender, any ambiguities in rates quoted by the tenderer in
words or figures;
- (v) Should specifically record whether samples have
been supplied or not alongwith the tender. (c. f. para 608 F).
1250. The names of the tenderers and the rates
quoted by each tenderer should be read out, wherever practicable, to the
tenderers or the representative who may be present at the time of opening of
the tenders. While opening the tenders, no opportunity should be given to any
tenderer to repudiate, amend or explain the rate and or any condition quoted in
the tender. No tenders should be entertained from any party in his private capacity
who is directly or indirectly connected with Government service, or for which
the specified earnest money has not been received (c f. para 609 F.)
1251. Delayed and late tenders''--Delayed' tenders i. e., "tenders"
received before the time of opening but after the due date and time of receipt
of tenders should also be opened and dealt with in the same manner as tenders
received before due date and time. "Late" tenders i.e.,
tenders received after the specified time and of opening should be opened by
the concerned Branch Officer and marked distinctly preferably in red ink,
prominently on the envelope as well as on the tender papers. A suitable remark
in regard to both delayed and late tenders should be made both in the Tender
Register as well as in the comparative Statements. For dealing with
"Delayed" and "late" tenders separate instructions as
issued by the Railway Board from time to time should be followed, (c f. para
610 F).
1252. A statement of comparative rates and other
important tender conditions should be prepared by the branch concerned and
verified by the Accounts Department. It must be ensured that all tenders
received are tabulated in the above comparative statement and put to a Tender
Committee constituted for the purpose for consideration without any screening
by any other official (c.f. para 611 F.)
1253. Briefing notes for the Tender Committee--Alongwith the tabulation statement a briefing
note duly authenticated at an appropriate level should be submitted clearly
indicating the following details :
- (i) Complete and latest information with regard to
lowest contract rates for the same or similar materials or work for the
particular or continguous area;
- (ii) The conditions of supply or undertaking to work
with reference to information under item (i) above;
- (iii) The latest data in regard to the availability of
materials and prices thereof and the working conditions etc. to co-relate
the present quotation with those obtained earlier;
- (iv) Any special condition attached to the rates and
works or supplies referred to in (i) above as well as technical data
required for dealing with the tenders under consideration; and
- (v) Any other relevant information worthy of
consideration in the contract (c f. para 612 F).
1254. Scrutiny by the Accounts Department.--The tabulation statement and the briefing notes
shall be sent thereafter for scrutiny together with the original tenders to the
Accounts Officer concerned. The tabulation statement should be signed by the
Section Officer (Accounts) nominated for the purpose in token of his
verification (c f. para 613 F).
1255. Constitution of Tender Committee.--Tender Committee should be generally constituted
by the authority competent to accept the tenders where the tender value
involves more than Rs. 10,000. When the General Manager is authority competent
to accept the tender, the Head of the Department concerned should arrange to
constitute the Tender Committee. (c f. para 614 F).
The Tender Committee
should consist of a minimum three members of whom one should be from the
Accounts department and one from the concerned executive department. The third
member should be from another department which also deals with such contract
matters (c. f. para 615 F).
The Tender Committee
should be so constituted that an officer recommending acceptance of a tender in
his capacity as a member of the Tender Committee shall not also be the
accepting authority of the same tender. In such cases the officer concerned
should put up the Tender Committee's proceedings to the next higher authority
for acceptance, notwithstanding the fact that the Tender Committee's
recommendations are within his own powers of acceptance (c. f. para 616 F).
1256. Acceptance of tender.--An unqualified acceptance of a tender
constitutes a binding contract until a formal agreement is constituted and in
order to ensure this fact the acceptance letter should be suitably worded.
However, if the acceptance of the tender by the Railway is a conditional acceptance,
it requires the consent of the tenderer before the binding contract takes
place.
1257. Development Orders.--At certain times, contracts may have to be
placed to promote indigenous development of new technology/techniques. Such
contracts are called Development Orders and in the placement of such orders the
rules applicable normally in such cases can be relaxed and certain concessions
may by granted. The concessions may include (i) an advance commitment for
placement of orders to meet the future demand for a period of 2 or 3 years
provided the rates/prices are reasonable; (ii) a commitment indicating a
progressively diminishing quantum of orders for a specified period. The
rate/price to be accepted will depend on factors like nature of item/work development
cost involved etc. and price preference evaluated on individual cases on the
merits of the case.
1258. Agreement Forms.--The Form of Agreement may in cases the tenders
are invited be the Tender Form itself; the Conditions of Contract,
Specification etc. may be embodied in the Agreement Form or may be an annexure
thereto; or may be provided, they are readily accessible to the contractor, be
merely referred to therein. On behalf of the contractor the signature of only
such person or persons as are competent to bind him legally shall be accepted
on a contract. (c. f. paras 414S and 436S).
1259. Signing of Agreements.--For entering into any contract of the value
higher than Rs.1 crore prior approval of the Railway Board should be taken. The
General Managers are empowered to sign contracts on behalf of the President for
approved and sanctioned works costing over Rs.1 crore each after the Board's
approval has been obtained to the terms and conditions thereof and also to sign
any subsidiary agreement in respect of such contracts.
No authority may enter
into contract which is beyond the limits of its financial powers. Subject to
any restrictions or limitations which may be imposed by the General Managers,
the powers vested with the General Manager may be delegated to subordinate
authorities. On behalf of the President, contract can be signed by only such
authorities as have been empowered to do so vide Appendix II to the Indian
Railway Code for the Stores Department.
Note.-- For the purpose of this paragraph girders,
structural steel works, rolling stock and other like material which will
involve manufacture come under the category of `works' and not `stores'.
1260. Execution of contract prior to commencement of works or
supplies:-
- (i) No contractor should be permitted to commence work
or supply materials until the relevant contract or work order has been
signed by the parties competent to do so;
- (ii) Exceptions to this rule are permissible only in
cases of extreme urgency such as work or supplies necessary to safeguard
life or property or to repair damage to a track caused by flood, accident
or other unforeseen contingency; so as to restore and maintain through
communication. Even in such case, if circumstances, permit, some form of
written contract or at least an agreed statement of rates to be paid
should be prepared before the commencement of works or supplies, the
intention being that the conditions, specifications, etc. with sufficient
items and rates to carry on with, should be agreed upon hand.
- (iii) In other exceptional but less emergent cases in
which the commencement of work or supply cannot be postponed till the
preparation and sanction of the contract documents, prior consultation
with the Financial Adviser and Chief Accounts Officer shall be necessary.
- (iv) In all cases of departure from sub-para (i) above,
the completion and execution of the main contract should be proceeded with
expeditiously. (cf. pra 627 F)
1261. Refund of earnest money.- The earnest money of all unsuccessful
tenderers should be refunded as expeditiously is possible. The earnest money deposited
by the successful tenderer, if he so desires be appropriated towards the amount
of security to he furnished by him.
II Management of Contracts
1262. Agreements and Work Orders.- As soon as possible
after the acceptance of a tender, the successful should be called
upon to furnish the required security (refer para 1244) and to sign the formal
Agreement or Work Order. For zone-contracts separate Work Orders are issued for
each specified work under Agreement. For contracts for specific works, the
contract document required to be executed by the tenderer whose tender is
accepted shall be either an Agreement or work Order.
1263. All Work Orders and Agreements executed
against a tender should be noted on the tender with a view to see that the
amount of tender is not exceeded beyond the powers of the authority
who accepted it. An Agreement/Work Order Register may be maintained in the
following form :-
1264: Advances to Contractors -
It shall be duty of the Executives to abstain as
far as possible from giving advances and they should endeavor to maintain a
system under which no payments are made except for work actually done. General
Managers may, however. sanction advances within their delegation of powers, as
per limits indicated hereunder for such of the works which are capital
intensive and of specialized nature, if the estimated value of the tender
exceeds Rs. 25 (twenty five) crore. Suitable provisions may be included
in the special conditions of the tender for grant of Mobilisation Advance
and advance against machinery and equipment, if the work warrants grant of such
advances, subject to conditions stated hereunder:
(a): Mobilisation Advance -
This shall be limited to 10% of the Contract
value and payable in 2 stages as indicated below:
Stage I – 5% of Contract Value on signing of the
contract agreement.
Stage II - 5% on mobilization of
site-establishment, setting up offices, bringing in equipment and actual
commencement of work.
The 1st stage of advance shall be payable
immediately after signing of contract documents. The 2nd stage of advance
shall be payable at the time of mobilization, after submission of a utilization
certificate by the contractor that the Stage 1 advance has been properly utilized
in the contract.
(b): Advance Against Machinery and Equipment·
This advance shall be limited to a maximum of
10% of the contract value against new Machinery & Equipment, involving
substantial outlay, brought to site and essentially required for the work. This
advance shall not exceed 75% of the purchase price of such Equipment and shall
be payable when hypothecated to the President of India by a suitable bond or
alternatively covered by an irrevocable Bank Guarantee for full cost of
the Plant & Equipment from a Nationalised Bank in India or the State Bank
of India in a form acceptable to Railways. The Plant & Equipment shall be
insured for the full value and tor the entire period, they are required for the
work. This Plant & Equipment shall not be removed from the site of work
without prior written permission of the Engineer. No advance should be given
against old Plant & Machinery.
(c): Advances for accelerating
progress of the work during course of execution of Contract .,
This advance is to be decided on the merits of
each case and shall be restricted to a maximum of 5%, of contract value. This
is to be granted by the General Manager on the recommendations of the Chief
Engineer in-charge, in consultation with the Associate Finance, While recommending
this advance for sanction of General Manager, the Chief Engineer in-charge
shall also confirm that progress of the contract work has been as per
milestones/ targets laid down and no extension to Date of completion of the
contract has been given on contractor's account.
(d): Advances in Exceptional Cases
General Managers are further empowered to grant
advances in exceptional cases upto a maximum of Rs, 20 lacs in respect of even
contracts of value less than Rs 25 crore, if considered absolutely essential,
depending on the merits of each ease and circumstances in each situation, to be
recommended by the Chief Engineer in-charge and in consultation with the
Associate Finance.
1264 (e) The above advances are subject to the
following conditions
(i) The advance shall carry an interest at the
rate to be decided by the Railway Board and communicated at the beginning of
every financial year, to be applicable for the tenders to be opened in that
financial year.
(ii) Advances except those against machinery and
equipment, shall be payable against irrevocable guarantee (Bank Guarantee,
FDRs, KVPs /NSCs) of at least 110% of the value of the sanctioned advance
amount (covering principal plus interest). The Bank Guarantee shall be from a
nationalized Bank in India or State Bank of India in a form acceptable to
the Railways;
(iii) The recovery shall commence when the value
of contract executed reaches 15% of original contract value and shall be
completed when the value of work executed reaches 85% of the original contract
value. The installments on each "on account bill" will be on pro-rata
basis;
(iv) That the grant of advance is
primarily in Railway's own interest;
(v) That a contract does not receive
advances for same work from different officers:
(vi) That arrangements are made with the
Accounts Officer for proper accounts being kept with regard to payment and
recovery of these advances; and
(vii) That all necessary precautions are taken
to secure Government from the possibility of loss and for preventing the system
becoming more general or continuing longer than what may be absolutely
necessary for proper progress of the work.
1264 (f): Method of Recovery of interest
Interest shall be recovered on the advance
outstanding for the period commencing from the date of payment of advance till
date of particular on-account bill (through which recovery of principal is
effected) and adjusted fully against on-account bill along with pro-rata
principal recovery. In the event of any short-fall, the same shall be carried
forward to the next on-account bill and shall attract interest.
The Bank Guarantee for such advances shall
clearly cover at least 110% of the value of the sanctioned advance amount
(covering principal plus interest).
1265. Variation of Contract Conditions.-The power
to vary the terms of a contract lies only with actual parties thereto. The
contractor and his sureties, if any, must, therefore, be consenting parties to
all variations which should be the subject of a subsidiary agreement stating
what is to be varied and what will remain unchanged in the original contract.
The drafting of this agreement should be the subject of careful scrutiny to
ensure that the conditions, specifications etc. of the main contract are
adequate for and applicable to the variation or that the latter is made
self-sufficient in these respects. Such subsidiary agreement should be regarded
as fresh contracts and entered into before effect is given to the variation.
The contract conditions may be varied by various authorities competent to do so
to the extent shown below :
(a) Variation of the conditions of contract.--These may be varied with the sanction of the
authority that approved the original contract acting in consultation with his
Financial Adviser and after taking legal advice, if necessary.
(b) Variation of the Rates or Items.--Contracts
in which a price variation clause is included, the rates may be varied by the
authority which approved the original contract with the concurrence of his
Financial Adviser. If the total value of the contract after allowing for the
variation is beyond the powers of the authority which approved the original
contract, a sanction of the higher authority within whose competence as to
amount it lies should be obtained.
(c) Variation of the Quantities of any
Items.---These may be varied by the authority which approved the original
contract to the extant deemed necessary, provided that Indian Railway Code
Rules relating to control over expenditure are not contravened thereby and
provided also that the total value of the amended contract does not exceed the
powers of the authority that approved the original contract. However, in the
case of contracts approved by the G. M. or higher authorities quantities of any
item may be varied to a reasonable extent by the Chief Engineer-in-charge.
Where materials are required during a contract
period in excess of the quantities contracted for and such excess is not
sufficiently large to justify the invitation of fresh tenders, there is no
objection to quantities under the existing contract being increased suitably,
Efforts should, however, be made to secure more favourable terms for the
increased quantities.
(d) Variation of the Items.--These
may be varied at discretion of the authority which approved the original
contract to the following extent, viz., existing items may be deleted or
additional items inserted at rates, which agreeable to in general or specific
orders at the time being in force, may be decided by the authority making the
variation; subject only to the two provisions of Rules in sub-para (c) above.
However, in the case of contracts approved by G. M. or higher authorities,
powers for such variation shall lie with Chief Engineer-in-Charge (c f. para
628 F).
Note :-- Variation to be approved should be
limited so as not to completely change the scope, character and purpose of the
original contract.
1266. Extension of completion period.--The extension of completion periods may be
sanctioned at the discretion of the authority which signed the original
contract provided :
- (i)
that the rate in contract was not accepted against other lower tenders in
consideration of the date of completion;
- (ii)
that he is satisfied that the delay will not cause loss or damage; and
- (iii)
that in case it does not satisfy any or both of the above conditions such
sanction shall be given only in consultation with his Financial Adviser
after taking legal advice, if necessary. (c f. para 445 S.)
1267. Liquidated Damages.--It would be necessary for the Railway to serve
on the contractor a notice of the intention to recover liquidated damages as
required under the contract Act even though the contractor has been apprised of
this liability earlier. The Railway can, however, recover by way of liquidated
damages only reasonable compensation not exceeding the amount so named or
stipulated in the contract. The compensation shall be computed on the basis of
the actual loss sustained by the railway or the inconvenience that has been
occasioned by the failure of the contractor even though no loss has actually
been caused. The decision for recovery of liquidated damages should not be
taken at a level lower than the authority who signed the contract.
1268. Variation in quantity of work during the
execution of work.--If during the execution
of a work the initial quantities of work are expected to vary substantially a
check should be made immediately by comparing the value of the revised work as
per the rates quoted by the original tenderers to determine whether the
decision to award the contract to a particular tenderer is vitiated by the
variation in quantities. A variation between 15 to 25% depending on the nature
of the particular category of work to be done would not be considered as
unreasonable. If such a variation of the award of the contract as between
tenderers is noticed, the railway administration should immediately examine
whether it is practicable to bring in a new agency to carry out the extra
quantity of work keeping in view the progress of the work on the original
contract and the nature and lay-out of the work. If such a course is not
practicable, the reasons for the same may be recorded and approved by the
competent authority and negotiation should be carried out with the existing
contractor for arriving at a reasonable rate for the additional quantities of
work. If, however, it is found that there will be no serious practical
difficulty in meeting the additional quantity of work done by another agency,
one of the following two alternatives, as found feasible may be adopted :--
- (i)
inviting fresh tenders for the extra quantity:
- (ii)
negotiating the rate for the extra quantities not only with the existing
contractor, but also with all the tenderers who had initially quoted for
the work.
1269. Materials issued to the contractors.--The issue of materials to the contractors should
be solely for the bonafide requirements of Government Works. The total issue
for any particular work should be limited to the reasonable needs of that work.
This precaution is particularly necessary when the issue rates are lower than
the prevailing market rates or the latter are expected to rise appreciably. In
cases where large issues are involved, strict watch should be maintained that
the aggregate of quantities of any or all materials issued to a contractor from
time to time for use on a work remains within the estimated requirements of his
contract. The contract or the Work Order should specify the materials to be
supplied by Government for use on the works and the rates to be charged to a
contractor for such materials should also be definitely specified, vague
quotations such as (at stock rates) being avoided. If materials outside the
contract are supplied for use on a work on the application of a contractor or
are used in excess of requirements, the Divisional Officer, should specify in
each case, the rate to be charged, which should be the market rate prevailing
at the time of supply of issue rate, whichever is higher plus departmental
charges, which shall be computed in accordance with paragraph 2329-S. When
materials outside the contracts are issued to a contractor, an acknowledgement
of the receipt of the materials should be taken from him. The acknowledgement
should be serially numbered and prepared in 'triplicate'-- one copy being
retained as office copy, one copy for posting the contractors ledger and the
third copy as a voucher in support of the recovery made in contractor's bill.
1270. Termination of Contract.--Decisions regarding the termination of contract
and execution of the balance work at the risk and cost of the contractor should
not be taken at a level lower than that of the authority who signed the
contract.
1271. Enforcement of Contract Conditions.--It is the duty of all authorities concerned with
the execution or carrying out of contracts to see that the terms of such
contracts are strictly enforced and that nothing is done by them that would
tend to nullify or vitiate a contract. (c f. para 452-S).
1272. Stamp Duty.--Contracts are exempted from Stamp Duty in cases
where Government (as opposed to the contractor) would, but for this exemption,
be liable to pay such duty. (c f. para 454-S).
1273. Responsibility of Railway Officials.--The employment of a contractor in no way
relieves the authorities concerned from the responsibility as to the standard
of progress of the work. (c f. para 457-S).
1274. Arbitration.--In the event of disputes between the contractor
and the railway in a contract the matter may be referred to arbitration as
provided for in the conditions of contract. When, however, a contractor has
received all payments in respect of all his bonafide claims and has given a `No
Claim' Certificate, but puts in fresh claims and demands a reference to
arbitration, the Railway Administration will be justified in refusing
arbitration in such cases. It is, however, advisable to take legal opinion
before finally rejecting the demand for arbitration.
1275. Arbitration Awards.--All Arbitration Awards shall be executed on
stamp paper in accordance with the Stamp Duty Act.
1276. Acceptance of Arbitration Award.--Where the Railway Administration decides to
accept an arbitration award, it is not necessary to cause an award to be filed
in a court in order to make payment to the party concerned. The party should,
however, be asked to give in writing their willingness to accept the payment in
full and final settlement of all claims and also furnish a `No Claim
Certificate' before effecting the payment, Railway Board should be informed of
payment to a contractor where as a result of the arbitrator's award, exceeded
by more than Rs. 50,000 the amount considered due by the Railway Administration
before the arbitration proceeding began.
In case of an award the railway has to realize
the amount from the contractor, the railway should on the merits of the case,
decide the course of action to be taken bearing in mind the provision of the
Limitation Act 1963 in regard to finalisation of the award.
1277. Legal Proceedings.--Before any legal proceedings arising out of
contracts are entered upon, the sanction of General Manager acting in
consultation with his Legal and Financial Adviser should be obtained. (c f.
para 451-S).
1278. Custody of Security Deposits.-The rules regarding custody of security deposits
are contained in chapter XVIII of the Indian Railway Code for the Accounts
Department (Part I). In the case of guarantee bonds, the Accounts Officer is
responsible for safe custody as well as for giving timely intimation (say three
months in advance) to the executive officer of the date of expiry of the
guarantee bond. The executive officer shall take action to extend from time to
time the validity of the guarantee bond for such periods as may be necessary in
relevance to the completion of the work or in subsequent period of maintenance
that may have been provided for in a particular contract. It will be the
responsibility of the Accounts Officer to encash the guarantee bond before its
expiry in case it is in necessary to take such step.
1279. Applicability of Contract Labour (Regulation
and Abolition) Act.-The provision of
Contract Labour (Regulation and Abolition) Act, 1970 should be followed
wherever required.
Multiple choice questions:
Question
1:
What is the definition of a
"Contract" according to the Indian Contract Act, 1872?
A) An agreement enforceable by law
B) A mutual understanding not necessarily enforceable by law
C) A verbal promise
D) An informal arrangement
Answer: A) An agreement enforceable by law
Question
2:
What are the primary conditions for
an agreement to be enforceable by law under the Indian Contract Act, 1872?
A) Mutual agreement and verbal
confirmation
B) Free consent, competent parties, lawful consideration, and lawful object
C) Written documentation and a witness
D) Consent of a legal authority
Answer: B) Free consent, competent parties, lawful consideration,
and lawful object
Question
3:
What does the agency of contractors
involve in the context of Indian Railways?
A) Overseeing the sale of tickets
B) Carrying out works of construction, repairs, or maintenance
C) Managing the financial accounts
D) Conducting safety inspections
Answer: B) Carrying out works of construction, repairs, or
maintenance
Question
4:
Which type of contract involves the
contractor agreeing to carry out work for a fixed total sum, regardless of the
actual quantities and kinds of work done?
A) Schedule Contract
B) Piece Work Contract
C) Lumpsum Contract
D) Zonal Contract
Answer: C) Lumpsum Contract
Question
5:
In which type of contract are unit
rates for various items specified, without reference to the total quantity of
work to be done?
A) Schedule Contract
B) Piece Work Contract
C) Lumpsum Contract
D) Special Work Contract
Answer: B) Piece Work Contract
Question
6:
What is the maximum contract value
for new works, additions, alterations, special repair works, and supply of
building materials under a Zonal Contract?
A) Rs. 1 lakh
B) Rs. 5 lakh
C) Rs. 10 lakh
D) Rs. 50 lakh
Answer: B) Rs. 5 lakh
Question
7:
What is the primary duty of the
Executive in the tender system?
A) To minimize costs regardless of
quality
B) To obtain the best value possible for the money spent
C) To avoid publicizing tender opportunities
D) To select contractors based on personal preference
Answer: B) To obtain the best value possible for the money spent
Question
8:
Under what circumstances may the
tender system be bypassed, according to the provided text?
A) When the project value is below
Rs. 10,000
B) In emergencies or with specific approvals from higher authorities
C) When the work is for routine maintenance
D) When the contractors are not available locally
Answer: B) In emergencies or with specific approvals from higher
authorities
Question
9:
Who is responsible for the final
approval of inviting limited tenders on open line railways for works costing up
to Rs. 40 lakhs?
A) General Manager
B) Financial Adviser and Chief Accounts Officer
C) Zonal Contractor
D) Head of the Engineering Department
Answer: B) Financial Adviser and Chief Accounts Officer
Question
10:
What is the primary requirement for
maintaining a list of approved contractors?
A) Contractors must provide a
guarantee
B) Contractors' capability and financial status must be verified
C) Contractors must be residents of the railway zone
D) Contractors must have a government certification
Answer: B) Contractors' capability and financial status must be
verified
Question
11:
Which of the following documents is
NOT typically part of a contract agreement?
A) Conditions of contract
B) Tender forms
C) Contractor's personal history
D) Specifications and drawings
Answer: C) Contractor's personal history
Question
12:
Which method of obtaining tenders
involves public advertisement in the most open public manner possible?
A) Limited Tender
B) Single Tender
C) Open Tender
D) Closed Tender
Answer: C) Open Tender
Q13. What should be done if standard conditions in a contract
prove defective?
a) They should be immediately
discarded.
b) The issue should be reported to
the Railway Board if they prescribed the conditions, or amended in consultation
with Legal and Financial Advisers.
c) The contract should be
terminated.
d) The contractor should be
penalized.
Answer: b) The issue should be reported to the Railway Board if
they prescribed the conditions, or amended in consultation with Legal and
Financial Advisers.
Q14. Who is responsible for approving unusual conditions of a
contract before they are imposed?
a) The contractor
b) The Railway Board only
c) The General Manager, in
consultation with Legal and Financial Advisers
d) The Chief Engineer
Answer: c) The General Manager, in consultation with Legal and
Financial Advisers
Q15. What is a lawful consideration in a contract?
a) A legal document signed by both
parties
b) An agreement that provides either
a positive or negative form of consideration
c) A contract that has a penalty
clause
d) A verbal agreement between
parties
Answer: b) An agreement that provides either a positive or negative
form of consideration
Q16. What should be done if time is to be "of the
essence" in a contract?
a) It should be stated generally
without specifics.
b) It should be specifically stated
in the contract.
c) It should be left to the
contractor's discretion.
d) It should not be mentioned to
avoid confusion.
Answer: b) It should be specifically stated in the contract.
Q17. What should be detailed if Railway materials are to be used
in a contract?
a) The color of the materials
b) The place or places at which they
will be delivered and the rate at which the value will be recovered
c) The contractor's opinion on the
materials
d) The estimated cost of storage
Answer: b) The place or places at which they will be delivered and
the rate at which the value will be recovered
Q18. Who is responsible for loss or destruction of Railway
property lent to a contractor?
a) The Railway Administration
b) The contractor, if it is
specified in the terms of the loan
c) The General Manager
d) No one is responsible
Answer: b) The contractor, if it is specified in the terms of the
loan
Q19. What should be done before special conditions are added to
standard conditions in a contract?
a) They should be immediately
implemented.
b) Their effect should be carefully
examined and any consequential changes should be made.
c) They should be approved by the
contractor.
d) They should be discarded if they
conflict with standard conditions.
Answer: b) Their effect should be carefully examined and any
consequential changes should be made.
Q20. What is the status of a contract if the contractor or
others on his behalf offer illegal gratification?
a) The contract becomes void.
b) The contract continues with a
warning.
c) The contractor pays a fine, but
the contract remains valid.
d) The contract is renegotiated.
Answer: a) The contract becomes void.
Q21. How should rates be entered in a contract?
a) In figures only
b) In words and figures, clearly
stating what they cover
c) In percentages only
d) In an appendix to the contract
Answer: b) In words and figures, clearly stating what they cover
Q22. What must tender forms supplied to tenderers include?
a) Only the name of the contractor
b) The contents of the contract
documents, either directly or by reference
c) A detailed history of the Railway
Administration
d) The contractor's past projects
Answer: b) The contents of the contract documents, either directly
or by reference
Q23. What must be done in cases of tenders involving foreign
exchange expenditure in excess of Rs. 50,000?
a) They must be handled by the
General Manager alone.
b) They require prior approval from
the Railway Board before tenders are called for.
c) They do not require any special
approval.
d) They should be avoided.
Answer: b) They require prior approval from the Railway Board
before tenders are called for.
Q24. How should the right to reject any or all tenders be
stated?
a) It should be implied.
b) It should be explicitly stated
without the need to assign reasons.
c) It should be left to the
contractor's discretion.
d) It should be included only if the
contract exceeds a certain value.
Answer: b) It should be explicitly stated without the need to
assign reasons.
Q25. What should be included in the tender notice regarding the
submission of tenders?
a) The contractor's personal details
b) The place, date, and time for
submission and opening of tenders
c) The estimated project duration
d) The number of contractors invited
Answer: b) The place, date, and time for submission and opening of
tenders
Q26. When open tender system is adopted, who can obtain tender
forms?
a) Only contractors on the approved
list
b) Only foreign contractors
c) Any contractor, on payment of the
prescribed fees
d) Only contractors who have
previously worked with the Railway Administration
Answer: c) Any contractor, on payment of the prescribed fees
Q27.What should the amount of
earnest money deposited be in a contract?
- A) Sufficiently large to be a security against loss
- B) Just enough to cover administrative costs
- C) A token amount not exceeding Rs. 1,000
- D) Determined by the contractor
Answer: A) Sufficiently large to be
a security against loss
Q28.What is the maximum amount of
earnest money required for works costing more than Rs. 50 lakhs?
- A) Rs. 35,000
- B) Rs. 50,000
- C) Rs. 75,000
- D) Rs. 100,000
Answer: B) Rs. 50,000
Q29.What action should be taken
if a tenderer withdraws their offer within the validity period?
- A) The tenderer should be fined
- B) The full earnest money should be forfeited
- C) The tender should be accepted with modifications
- D) The tenderer should be banned from future tenders
Answer: B) The full earnest money
should be forfeited
Q30.In what form should earnest
money NOT be accepted?
- A) Cash
- B) Demand drafts
- C) Guarantee bonds
- D) Government Securities
Answer: D) Government Securities
Q31.What is the required security
deposit for contracts costing up to Rs. 1 lakh?
- A) 5% of the contract value
- B) 7.5% of the contract value
- C) 10% of the contract value
- D) 15% of the contract value
Answer: C) 10% of the contract value
Q32.What is the maximum security
deposit for contracts above Rs. 2 crores?
- A) 7.5% of the contract value
- B) 5% of the contract value
- C) 10% of the contract value
- D) 3% of the contract value
Answer: B) 5% of the contract value
Q33.What should be done with
tenders received by post?
- A) They should be ignored
- B) They should be entered in the Tender Register and
the time of receipt recorded
- C) They should be opened immediately upon receipt
- D) They should be returned to the sender
Answer: B) They should be entered in
the Tender Register and the time of receipt recorded
Q34.Who should be present at the
time of opening tenders with a value above Rs. 10,000?
- A) The contractor
- B) The Accounts representative
- C) The General Manager
- D) The Legal Adviser
Answer: B) The Accounts
representative
Q35.What should be done with late
tenders?
- A) They should be ignored
- B) They should be opened and marked distinctly as
'late'
- C) They should be returned unopened
- D) They should be considered as valid tenders
Answer: B) They should be opened and
marked distinctly as 'late'
Q36.Who is responsible for the
scrutiny of the tabulation statement and briefing notes?
- A) The General Manager
- B) The Accounts Officer
- C) The contractor
- D) The Legal Adviser
Answer: B) The Accounts Officer
Q37.What is required for a
contract to be binding until a formal agreement is signed?
- A) An unqualified acceptance of a tender
- B) A verbal agreement between parties
- C) A written promise by the contractor
- D) The presence of a legal representative
Answer: A) An unqualified acceptance
of a tender
Q38.What are Development Orders
in the context of railway contracts?
- A) Contracts aimed at promoting indigenous development
of new technology/techniques
- B) Contracts exclusively for foreign suppliers
- C) Emergency contracts for immediate supply needs
- D) Contracts limited to infrastructure projects
Answer: A) Contracts aimed at
promoting indigenous development of new technology/techniques
Q39.When can a contractor
commence work before a formal agreement is signed?
- A) When there is a delay in administrative processes
- B) In cases of extreme urgency to safeguard life or
property
- C) If the contractor agrees to a verbal contract
- D) When the contractor provides additional security
deposit
Answer: B) In cases of extreme urgency
to safeguard life or property
Q40.What should be done with the
earnest money of all unsuccessful tenderers?
- A) It should be retained as a handling fee
- B) It should be refunded as expeditiously as possible
- C) It should be converted into a security deposit for
future tenders
- D) It should be used for administrative expenses
Answer: B) It should be refunded as
expeditiously as possible
Q41.What must the Tender
Committee include when preparing a statement of comparative rates?
- A) A list of all bidders' personal information
- B) A detailed technical evaluation of each tender
- C) Complete and latest information regarding lowest
contract rates for similar materials or work
- D) A summary of past performance of each bidder
Answer: C) Complete and latest
information regarding lowest contract rates for similar materials or work
Q42.Which of the following statements is true about agreements and work orders?
A) Work Orders are issued for specific works under zone-contracts.
B) The contract document for specific works can only be a Work Order.
C) A successful tenderer must sign a formal Agreement or Work Order before
furnishing the required security.
D) Separate Work Orders are issued for each specified work under the Agreement
for specific works.
Answer: C
Q43.Who is empowered to sanction advances within their delegation of powers for capital-intensive and specialized works if the estimated value of the tender exceeds Rs. 25 crore?
A) Chief Engineer
B) General Manager
C) Divisional Officer
D) Financial Adviser
Answer: B
Q44.What is the maximum percentage of the contract value that can be granted as Mobilisation Advance?
A) 5%
B) 10%
C) 15%
D) 20%
Answer: B
Q45.What is the maximum percentage of the purchase price of new Machinery & Equipment that can be advanced to a contractor?
A) 10%
B) 25%
C) 50%
D) 75%
Answer: D
Q46.Under what condition can the General Manager grant advances up to Rs. 20 lakhs in contracts valued less than Rs. 25 crore?
A) When recommended by the Chief Engineer in-charge
B) When approved by the Divisional Officer
C) When sanctioned by the Railway Board
D) When there are sufficient funds available
Answer: A
Q47.What is required for advances to be granted against machinery and equipment?
A) The equipment must be covered by an irrevocable Bank Guarantee.
B) The equipment must be insured for 50% of its value.
C) The contractor must provide a No Objection Certificate.
D) The equipment can be removed from the site without prior permission.
Answer: A
Q48.What must be ensured when varying the terms of a contract?
A) The contract can be varied without the consent of the contractor.
B) The variation should be subject to a subsidiary agreement.
C) The conditions of the main contract do not need to apply to the variation.
D) No legal advice is needed for varying the terms.
Answer: B
Q49.Which of the following authorities can vary the quantities of any items in a contract?
A) Divisional Officer
B) General Manager
C) Chief Engineer-in-charge
D) Financial Adviser
Answer: C
Q50.How is the interest on advances recovered?
A) It is recovered at the end of the contract.
B) It is recovered only if the contractor fails to complete the work.
C) It is recovered on the advance outstanding for the period from the date of
payment of advance until the date of the on-account bill.
D) It is not recovered if the work progresses as per schedule.
Answer: C
Q51.What is required for the execution of materials issued to contractors?
A) The total issue should be unlimited for any particular work.
B) The rates for materials should be specified vaguely, such as "at stock
rates."
C) The issue of materials should be solely for the bonafide requirements of
Government Works.
D) No acknowledgment is needed from the contractor for materials issued.
Answer: C
Q52.Who should sanction the termination of a contract?
A) The Divisional Officer
B) The authority who signed the original contract
C) The Financial Adviser
D) The Railway Board
Answer: B
Q53.When can the Railway Administration refuse arbitration?
A) When the contractor has not received all payments in respect of his
bonafide claims.
B) When the contractor has put in fresh claims after giving a 'No Claim'
Certificate.
C) When the arbitration clause is not included in the contract.
D) When the General Manager does not agree.
Answer: B
Q54.Who is responsible for the custody of security deposits?
A) The contractor
B) The Divisional Officer
C) The Accounts Officer
D) The Chief Engineer
Answer: C
Q55.In which case can an arbitration award be executed?
A) When the award is not in favor of the contractor.
B) Only after filing the award in a court.
C) When the contractor provides a 'No Claim' Certificate.
D) Without any written acceptance from the contractor.
Answer: C
Q56.Which of the following acts must be followed for contracts involving labor?
A) Indian Penal Code
B) Contract Labour (Regulation and Abolition) Act, 1970
C) Indian Contract Act
D) Railway Act
Answer: B